Clay Planning Board Sends Buckley Road Gas Station to Town Board 6-1, Minutes After Two Members Said They Couldn't Support It
The Clay Planning Board voted 6-1 on March 19, 2025 to forward a Sonbyrne Sales gas station and convenience store at Buckley Road and Dolshire Drive to the Town Board, even after two members said during polling that they could not recommend approval until Onondaga County finished reviewing the site's traffic. The board also unanimously advanced an amended Laurel Springs zone change and approved several sign permits.
●Case #2025-008 (Sonbyrne Sales, 7190 Buckley Road): special permit referral for a gas station and convenience store sent to Town Board, 6-1, after Karen Guinup and Michelle Borton said in polling they could not support it without a finished Onondaga County traffic study; Paul Graves cast the recorded dissenting vote
●Case #2025-002 (Laurel Springs, West Taft Road): zone change recommended to Town Board, 7-0, after the applicant added a community room, green space and park benches the board had requested
●Approved wall-sign permits for Elite Commercial/Davidson & Ford (#54,755, 7-0), Seven Brew Drive Thru Coffee's three wall signs (#54,776, 7-0) and Ocean State Job Lot in the former Big Lots building (#54,787, 7-0); took no action on a Seven Brew freestanding sign (#54,777), referring it back to the Codes Department
●Adjourned the Charge Smart EV/Townplace Suites amended site plan to April 23 after members questioned how many EV chargers already exist at the site and whether more could take up a quarter of the hotel's parking
●Adjourned the Tully's Tenders site plan (State Route 31) to April 9 after a majority of members said a proposed "No left turn" sign at the car wash exit would be unenforceable on private property
●Adjourned roughly a dozen other pending cases to April or May meetings, including Emerald Lawn Care, Amerco Real Estate, Equipment Share Syracuse, the Buckley Warehouse site plan and KRSM subdivision, Pack Rat Storage, Sears Property, Goguen Drive Realty, Inverness Gardens, Scott Merle Builders and J.W. Didado Expansion; the chairman said a letter would go to Equipment Share denying its case without prejudice absent an update
●Approved the February 26, 2025 meeting minutes, 6-0, with Chairman Mitchell abstaining because he was absent that day
The Clay Planning Board voted 6-1 on March 19, 2025 to forward a special permit for a Sonbyrne Sales gas station and convenience store at Buckley Road and Dolshire Drive to the Town Board — minutes after two of the board's own members said, one at a time, that they could not recommend approval until Onondaga County finished studying the intersection's traffic. The minutes do not explain why the recorded vote came out so different from what those members had just said out loud.
Christian Brunelle, vice president of Sonbyrne Sales, described a 4,232-square-foot convenience store and fueling facility planned for a 2.47-acre parcel at the northeast corner of Buckley Road and Dolshire Drive, in an RC-1 zoning district surrounded by North Medical Center, a town park, commercial properties and single-family homes. The site plan shows two access points on Buckley Road and one driveway onto Dolshire Drive, with the dumpster enclosure placed at the far end of the property away from the residential side of Dolshire.
Chairman Russ Mitchell said a family living near the site is concerned about the smell of gasoline. Brunelle said the canopy vents prevent that, that he has seen no such problems in eighteen years in the business, and that the fueling stations would sit about 250 feet from the residential area. During the public hearing, Jordan Popps, who lives at 146 Dolshire Drive next to the site, told the board that Dolshire has children who play and ride bikes, and that he was concerned about traffic and noise from the new ingress and egress, air quality from the tanks and dumpster, evening lighting, and the store's planned 24-hour operation.
Approval also depends on Onondaga County, which had asked for a traffic study, a lighting plan, sidewalk plans and sewer connection details before the project moves forward. Deputy Chair Michelle Borton read the county's position into the record: "The Onondaga County Department of Transportation has determined that the applicant must contact the Department to discuss any required traffic data for the proposed project. The municipality must ensure any mitigation as may be determined by the Department is reflected on the project plans prior to, or as a condition of, municipal approval." Borton said the county's eventual ruling on the Buckley Road and Dolshire Drive access points would decide whether the site's truck turns are workable at all, and recommended settling that before the special permit is granted. Karen Guinup agreed, adding that any traffic study should also weigh Dolshire Drive improvements the town has already approved.
When Mitchell polled the board member by member on the special permit, Al McMahon, Jim Palumbo and Hal Henty said yes; Henty cited Sonbyrne's history on past town projects. Paul Graves voted no. Guinup said the permit should not be granted "without traffic study being done and Onondaga County giving their firm approval/disapproval of full access to Buckley Road." Borton said she could not recommend approval "until Onondaga County transportation coordination is done and we are certain of the traffic impact." Mitchell voted yes last, saying the project would improve the corner and that most customers would be nearby residents using Dolshire Drive rather than the highway — but he added that the Town Board still needs an agreement between the county and the town on the traffic situation before final approval.
Moments later, McMahon moved to recommend the special permit to the Town Board on standard referral form #60, Palumbo seconded, and the motion carried 6-1.
The recommendation now goes to the Town Board. By the board's own account, the outstanding question is unchanged from the polling: Onondaga County's transportation department has not yet completed the traffic review of the Buckley Road and Dolshire Drive access points that multiple members called necessary before the project can be considered settled.
Minutes report. Drafted by our AI minutes pipeline from the official minutes — the board's own record of the meeting — and checked against that record by an automated verification gate before publication.
●McDonald's USA LLC special permit referral (Case #2025-011, 4979 West Taft Road) adjourned to April 23, 2025 (6-0) after Chairman Russ Mitchell said no referral would be given this evening, citing the Wegmans Plaza's internal traffic circulation; he asked for one drawing showing the full plaza from the traffic signal to Cedarpost.
●Northern Credit Union special permit (Case #2025-010, 5004-5008 West Taft Road) withdrawn because the Town Board has not yet referred it to the Planning Board; the chairman said the Town Board is reviewing zone clarification for the site.
●Packaging Corp. of America site plan (Case #2025-012, 4471 Steelway Blvd.) for a 32,500 sq. ft. and a 725 sq. ft. addition adjourned to April 23, 2025 (6-0); the board flagged a required SPDES permit, an Indiana Bat habitat study, and asked for replacement deciduous trees.
●KRSM Subdivision Buckley Warehouse (Cases #2024-012 and #2024-013, 4583 Buckley Road): board adopted a negative SEQR declaration (6-0), moved the case to final plat (6-0), and granted final plat approval (6-0).
●J.W. Didado Expansion amended site plan (Case #2024-057, 7822 Morgan Rd.) approved 6-0, conditioned on legal and engineering requirements.
●Pack Rat Storage amended site plan (Case #2024-050, 4717 Wetzel Road) adjourned to May 14, 2025 (6-0) after board member Karen Guinup said she would not support approval until the owner removes illegal advertising signage and brings the site into code compliance.
●Inverness Gardens site plan (Case #2025-001, 4938 West Taft Road) adjourned to June 11, 2025 (6-0); Mitchell said Onondaga County cannot yet clarify plans for right-in/right-out access on that corridor.
●Additional cases adjourned to April 23, 2025 (all 6-0): the Wegmans Great Northern hotel site, Equipment Share Syracuse, Sears Property preliminary and final plat, Tully's Tenders, and Scott Merle Builders preliminary and final plat.
●Two sign permits approved 6-0: a wall sign for Evolve Fitness at 4979 West Taft Road (Permit #54,803) and a wall sign for Theo Petros Greek Food at 7421 Oswego Road (Permit #54,823).
●Meeting adjourned at 9:21 p.m. (6-0); next meeting set for April 23, 2025.
Wegmans-Site Hotel Hits Wetland and Parking Objections as Clay Planning Board Adjourns Every Case
●Approved the minutes of the Feb. 12 Regular Meeting. Motion Carried: 6-0.
●Case #2025-006, Scott Merle Builders, 8835 Gaskin Road: preliminary plat to split a 1.81-acre parcel into a 0.56-acre and a 1.25-acre lot; adjourned to March 19 pending topography, flood-elevation and easement clarifications. Motion Carried: 6-0.
●Case #2024-050, Pack Rat Storage, 4717 Wetzel Road: amended site plan adjourned to March 19 at the applicant's request. Motion Carried: 6-0.
●Case #2023-053, proposed hotel at the Wegmans Great Northern site, 3955 State Rte. 31: board member Jim Palumbo questioned an EAF finding of no wetlands and asked whether an actual wetland delineation had been done; member Karen Guinup called the plan to bank one-third of the hotel's parking "totally unacceptable"; 103 rooms require 155 parking spaces per Guinup; board also flagged an encroachment into a National Grid easement and an unresolved snow-storage plan. Adjourned to April 9. Motion Carried: 6-0.
●Case #2024-070, Tully's Tenders, 3567 State Rte. 31: applicant defended its existing curb cut as DOT-reviewed and safe, but members Hal Henty, Paul Graves and Al McMahon each said they still consider the driveway configuration unsafe; Onondaga County Planning Board (OCPB) also raised sewer-connection and plumbing-permit requirements. Adjourned to March 19. Motion Carried: 6-0.
●Case #2025-001, Inverness Gardens, 4938 West Taft Rd.: adjourned to March 19 after the county rejected the applicant's proposed right-in/right-out access point; no new drawings will be produced until access is resolved. Motion Carried: 6-0.
●Cases #2025-003 and #2025-004, John E. Fisher Construction Co., 4593 Wetzel Road (site plan and special permit): adjourned to April 9. Motion Carried: 6-0.
●Case #2024-057, J.W. Didado Expansion, 7822 Morgan Road: amended site plan adjourned to March 19. Motion Carried: 6-0.
●Case #2025-007, Scott Merle Builders, 8835 Gaskin Road: final plat adjourned to March 19. Motion Carried: 6-0.
●Four sign permits approved as submitted, all Motion Carried: 6-0: two wall signs for Community Bank at 7379 Oswego Road; one wall sign for 7 Days Nails Spa at 4599 State Route 31; one wall sign for Momentum Strategic Wealth LLC at 4100-4160 State Route 31; one wall sign for an AT&T location at 3812 Brewerton Road.
●Tully’s Tenders (Case #2024-070), 3567 State Route 31: site plan approved 5-2, with Mr. Henty and Mr. Graves voting no over Route 31 traffic safety; a SEQR negative declaration was adopted 7-0; conditions exclude wall signage from the approval and bar a building permit until the drainage easement is filed.
●Northern Credit Union (Case #2025-010), 5004-5008 West Taft Road: board voted 6-1 to recommend the Town Board deny the requested NC-1 zone change, favoring the applicant’s own less-intense O-2 proposal; residents Sandy Laurenti and Anna Markopolsky raised traffic and landscaping concerns.
●Chairman Mitchell announced that, citing a rising caseload tied to Micron’s arrival — with some applications dating to 2023 — adjournments will no longer be granted meeting-to-meeting but must be pushed out at least two meetings.
●Equipment Share Syracuse (Case #2023-047), 7481 Henry Clay Blvd.: adjourned to May 14, its ninth adjournment; the code enforcement commissioner noted a special use permit is still needed for the site’s fuel storage tanks.
●Mike Tormey’s Buckley Road warehouse (Case #2023-052), 4583 Buckley Road: adjourned to May 14, its twelfth adjournment, after the town engineer required drawing corrections.
●Proposed hotel at the former Wegmans Great Northern site (Case #2023-053), 3955 State Route 31: adjourned to May 28 at the applicant’s request, its fifth adjournment.
●Seneca Savings (Case #2025-014), 5332 State Route 31: special permit referral for a bank with a two-lane drive-thru recommended to the Town Board 7-0.
●Justin’s Canine Campus (Case #2025-017), Market Fair North on Route 31: special permit for an 80-to-100-dog daycare recommended 7-0.
●Extra Space Storage, 7711 Henry Clay Blvd.: one wall sign and one freestanding LED sign approved 7-0.
Clay Planning Board Presses Fuel-Tank Applicant on Claim That No State Permit Is Needed
●Adjourned Goguen Drive Realty's special permit application for a fuel-tank contractor's yard on Goguen Drive to March 19, after the chairman disputed the applicant's claim that no DEC bulk-storage permit is required and the town attorney raised an unresolved 180-cumulative-day DEC rule — 7-0
●Adjourned the Charge/Smart EV/Townplace Suites amended site plan at 8505 Carling Road to March 19 pending written ADA parking documentation from the applicant — 7-0
●Adjourned John E. Fisher Construction's special permit and site plan for 4593 Wetzel Road to Feb. 26, after board members raised wetlands-boundary and stockpile-labeling concerns — 7-0
●Adopted a resolution granting site plan approval for Whitestone Apartments on State Route 31, the case's ninth adjournment, conditioned on legal and engineering sign-off — 7-0
●Adjourned Amerco Real Estate's amended site plan for 8015 Oswego Road to March 19 — 7-0
●Adopted a negative SEQR declaration and a site plan resolution for the Syracuse Pistol Club's amended site plan at 8042 Henry Clay Blvd. — 7-0 on each motion
●Approved a 37.75-square-foot wall sign for Metropolitan Signs/Stryker at 4522 Morgan Place, Permit #54,748 — 7-0
●Held over Community Bank's three-sign package for 7379 Oswego Road because only two signs are allowed by code; no vote taken
●Approved a 25.4-square-foot freestanding sign for Allied Sign/Bank of America at 3782 Route 31, Permit #54,747 — 7-0
●Approved the Jan. 29, 2025 meeting minutes and adjourned the meeting at 8:38 p.m.; next meeting Feb. 26, 2025 — 7-0
Clay Planning Board Opposes Twin Drive-Thrus at Lawton Road Corner, But the Town Board Has the Final Say
●Mirabito Energy Products (Cases #2024-048, #2024-049), Lawton Road at Route 31 — special permit referrals for drive-thru lanes at a proposed bank and coffee shop: after five residents spoke against the plan, six of seven board members individually said no in a hearing-floor poll (Palumbo held a mixed position, favoring the coffee shop drive-thru over the bank's); the board's formal action was a 7-0 vote to forward its members' comments and concerns to the Town Board, which controls the referral.
●Trinity Assembly of God (Case #2024-032), 4398 State Route 31 — amended site plan: SEQR negative declaration adopted 7-0; site plan resolution adopted 7-0, conditioned on legal and engineering approval.
●EV Charging Station/Panera (Case #2024-052), 3815 NYS Route 31 — amended site plan: SEQR negative declaration adopted 7-0; site plan resolution adopted 7-0.
●McDonald's USA (Case #2024-041) special permit referral for the Cedar Post Road/West Taft Road corner was withdrawn after the Town Board denied it.
●Summit Federal Credit Union (Case #2024-063), 5047 W. Taft Road — site plan adjourned to March 19; Chairman Mitchell objected that the applicant had altered the access design at County DOT's request without informing the board first.
●Tully's Tenders (Case #2024-070), 3567 State Route 31 — drive-thru site plan adjourned to Feb. 26; members again raised concerns about the right-in/right-out access on Route 31, a configuration state DOT had already declined to change.
●Inverness Gardens (Case #2025-001), 4938 West Taft Road — 88-unit senior housing site plan adjourned to Feb. 26 pending changes to dumpster placement and a clearer accounting of parking versus EV-charger spaces.
●Five sign permits — Fastsigns (Carling Road), Urban Pho and Mochinut (Oswego Road), Eastern Shore Park (two signs) and Bank of America (two signs) — all approved 7-0.
●Several other cases were adjourned without action: the Buckley Warehouse/KRSM subdivision matters (three cases) to March 19; Whitestone Apartments to Feb. 12 pending a signed agreement; Pack Rat Storage and the JW Didado expansion to Feb. 26; Syracuse Pistol Club to Feb. 12; and the Sears Property preliminary and final plats to March 19.
Clay Planning Board Picks Trees Over Fence at Pack Rat Storage, but Can't Get a Straight Answer on What's Actually Stored There
●Case #2024-050, Pack Rat Storage (4717 Wetzel Road): Chairman Mitchell polled board members individually on trees versus a vinyl fence along the property; six members (Henty, Borton, Graves, Palumbo, McMahon, Mitchell) favored trees, one (Guinup) favored the fence, calling the black mesh option "abominable." Resident Janet Rathburn said she has seen pallets, construction trailers and a backhoe stored on site, contradicting the applicant's answer that RVs and boats would be stored there; Commissioner Tessier noted the I1 zoning is for indoor storage and a special permit is needed for outdoor storage. Adjourned to July 23, 2025, 7-0.
●Cases #2024-065/#2024-066, Sears Property (9417 Horseshoe Island Road): Board adopted a SEQR negative declaration and granted final plat approval, both 7-0, conditioned on legal/engineering sign-off and recording of an access easement before any building permit issues.
●Case #2024-068, Goguen Drive Realty (7835 Goguen Drive): At a public hearing on a special-permit referral for six empty fuel tanks tagged "DO NOT FILL," Mr. Henty said the property's history shows the applicant "cannot be trusted and truthful" and that he does not trust the site; Mr. Graves and Mr. Palumbo separately raised concern that a proposed 1000-gallon refueling station could block trucks entering the site. Adjourned to May 28, 2025, 7-0.
●Case #2024-069, Charge Smart EV/Towneplace Suites (8505 Carling Road): Ms. Borton said the site plan had been altered and read into the record the state requirement that an altered engineered document be re-stamped and marked "altered by" the responsible engineer; the applicant's representative said she would address the seal and other drawing corrections. Adjourned to June 11, 2025, 7-0.
●Cases #2025-021/#2025-022, Windsor Property Group (7985 Morgan Road): A February zone change to R15 created a septic-system conflict; Chairman Mitchell suggested reverting to R40 to resolve it, while board attorney Bennett said a use variance would require a showing of economic hardship. Adjourned to June 11, 2025, 7-0.
●Case #2025-001, Inverness Gardens (4938 West Taft Road): Chairman Mitchell said the developer is seeking other financing; the board voted 7-0 to notify the applicant the case will be denied without prejudice if no response is received by the May 28, 2025 meeting.
●Three sign permits approved, each 7-0: a freestanding and canopy sign for Empower Parkinson/Engage Therapy & Wellness (4886-4888 West Taft Road); a wall sign for Excellus Resource Center (7421 Oswego Road); and a wall sign for Marcel's Ice Cream (4599 State Route 31).
●Roughly a dozen other cases, including Seneca Savings, Henry Clay Warehouse, Emerald Lawn Care, Amerco Real Estate, Equipment Share Syracuse, Buckley Warehouse and Scott Merle Builders, were adjourned without substantive discussion to dates ranging from May 28 through July 23, all by 7-0 votes.
Community Discussion
0 commentsBe the first to comment on this story.