PHONE: 315.435.3770 FAX: 315.435.3669 SYRACUSECENTRAL.COM Meeting Agenda June 6, 2017 8:00 AM Call to Order the Regular Meeting of the Agency A. Approval of Minutes – May 9, 2017 B. Treasurer’s Report C. Payment of Bills D. Conflict of Interest Disclosure Action Items
Randy Wolken, CEO MACNY will speak about CNY workforce development issues.
Old Thompson Road, LLC (Feldmeier Equipment) is requesting the Agency consider entering into a straight lease agreement for the project consisting of acquisition of 17 acres of vacant land, construction of a 130,000 square foot building that will house its offices and a streamlined manufacturing in the Town of DeWitt. Old Thompson Road, LLC is seeking exemptions from sales and use tax, mortgage recording tax, potential commencement of a payment in lieu of tax agreement (“PILOT”) and issue its revenue bonds.
Agency Actions Requested:
a. A Resolution of the Board describing the proposed project and the financial assistance the Agency may provide and authorizing a public hearing for the project. Agency benefits requested include a Payment in Lieu of Tax Agreement, exemption from sales and use tax and mortgage recording tax and issuance of its revenue bonds. b. A Resolution of the Board authorizing the execution of the Agent Agreement outlining the responsibilities of the Developer and Agency for the Project. Representative: Colby Clark, VP Operations, Dave Pollock, VP Sales, Sarah Stephens, Synapse
Cintas constructed a commercial/industrial cleaning facility (approximately 53,939 sq. ft.) The facility, employs over 100 employees and has plans to grow workforce by 3-5 employees per year for five years.
Agency Action Requested:
a. A request of the Board to approve an extension of time to complete the intial project Representative: Dan Colantuoni- Syracuse General Manager, Cintas
Tessy Plastics is in the process of building a 246,000 square foot manufacturing facility at its existing assembly and warehouse operation in the Town of Van Buren.
Agency Action Requested:
a. A Resolution of the Board for an amended SEQR for purposes determining that the project will not have a significant effect on the environment and requires no further environmental review.
Representative: Kevin McAuliffe, Barclay Damon
Representative: Steve Eckler, OBG
Representative: Holly Granat, Office of the Environment, Onondaga County Adjourn 2