  1. Appendix A: SEQRA Documentation and Agency Correspondence
  2. Appendix B: Traffic Analysis Report and Data
  3. Appendix C: Utility Provider Commitment Letters
  4. Appendix D: Visual Impact Assessment
  5. Appendix E: Noise Data

ONONDAGA COUNTY INDUSTRIAL DEVELOPMENT AGENCY

333 WEST WASHINGTON STREET, SUITE 130, SYRACUSE, NY 13202

PHONE: 315.435.3770  FAX: 315.435.3669  ONGOVED.COM Meeting Agenda May 6, 2021 10:45AM Call to Order the Special Meeting of the Agency A. Conflict of Interest Action Items 1. Review and discuss supplemental draft GEIS for White Pine Commerce Park and set public comment and hearing schedule.

Agency Action Requested:

a. Resolution to accept supplemental draft GEIS as adequate for public review, issue Notice of Completion of Supplemental Draft GEIS and authorization to OCIDA Staff and Counsel to take all necessary steps to comply with SEQRA

notice requirements;

b. Resolution to set a public hearing on the Supplemental Draft GEIS for May 24, 2021.

Representative: Robert Petrovich, Executive Director, OCIDA Adjourn

NEW YORK STATE ENVIRONMENTAL QUALITY REVIEW ACT (SEQRA)

DRAFT SUPPLEMENTAL GENERIC ENVIRONMENTAL IMPACT

STATEMENT

VOLUME I:

WHITE PINE COMMERCE PARK

5171 Route 31 Town of Clay, NY 13041

Lead Agency: Onondaga County Industrial Development Agency https://www.ongoved.com Robert M. Petrovich, Executive Director 333 W. Washington Street, Suite 130 Syracuse, New York 13202 315-435-3770 (Fax) 315-435-3669 Prepared by:

JMT of New York, Inc

19 British American Boulevard

Latham, NY 12110

518-782-0882

May 2021 Acceptance by the Lead Agency: _________________ Comments to be Submitted to OCIDA by: _________________ Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021

TABLE OF CONTENTS

Page Executive Summary………………………………………………………………….. ES.1 1.0 Introduction and Project Description………………………………………… 1.1 1.1 Project Background…………………………………………………….. 1.1 1.2 Changes in Circumstances…………………………………………........ 1.5 1.3 Permitting and SEQRA Process………………………………………… 1.7 2.0 Alternatives ……..…………………………………………................................. 2.1 2.1 Background……………………………………………………………… 2.1 2.2 Alternative 1: No Action Alternative …………………………………… 2.1 2.3 Alternative 2: The Park as Considered in the GEIS……………………… 2.2 2.4 Alternative 3: Smaller Expansion …..…………………………………… 2.3 2.5 Alternative 4: Develop Park in Alternative Location…….……………… 2.4 3.0 Environmental Setting………………………………………………………........ 3.1 3.1 Land Use & Zoning……………………………………………………… 3.1 3.2 Community Character…………………………………………................. 3.5 3.3 Transportation…………………………………………………………… 3.6 3.4 Utilities & Community Services………………………………………… 3.8 3.5 Topography, Geology & Soils…………………………………………… 3.9 3.6 Water Resources…………………………………………………………. 3.13 3.7 Air Resources……………………………………………………………. 3.15 3.8 Ecological Resources……………………………………………………. 3.17 3.9 Cultural & Archeological Resources……………………………………. 3.30 3.10 Visual Environment & Aesthetic Resources……………………………. 3.33 3.11 Noise ……………………………………………………………………. 3.34 3.12 Human Health…………………………………………………………… 3.37 4.0 Potential Environmental Impacts and Mitigation……………………………. 4.1 4.1 Land Use & Zoning……………………………………………………… 4.1 4.2 Community Character…………………………………………………… 4.2 4.3 Transportation …………………………………………………………… 4.3 4.4 Utilities & Community Services…………………………………………. 4.9 4.5 Topography, Geology & Soils…………………………………………… 4.13 4.6 Water Resources…………………………………………………………. 4.16 4.7 Air Resources……………………………………………………………. 4.19 4.8 Ecological Resources…………………………………………………….. 4.23 4.9 Cultural & Archeological Resources…………………………………….. 4.27 4.10 Visual Environment & Aesthetic Resources ……………………………. 4.28 4.11 Noise ……………………………………………………………………. 4.32 4.12 Human Health……………………………………………………………. 4.41 Table of Contents Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Page 5.0 Cumulative Impacts...……………………………………………...................... 5.1 5.1 Cumulative Impacts…………………………………………………….. 5.1 5.2 Mitigation……………………………………………………………….. 5.2 6.0 Unavoidable Adverse Impacts.…………………………………………........... 6.1 6.1 Unavoidable Impacts……………………………………………………. 6.1 7.0 Growth Inducing Aspects……………………………………........................... 7.1 7.1 Population Growth………………………………………………………. 7.1 7.2 Infrastructure Induced Growth………………………………………….. 7.1 8.0 Irreversible and Irretrievable Commitment of Resources………................ 8-1 8.1 Commitment of Resources………………………………………………. 8.1 9.0 Effects on Use and Conservation of Energy ………………………………… 9.1 9.1 Proposed Energy Sources………………..………………………………. 9.1 9.2 Anticipated Short-term/Long-term Energy Consumption .……..……….. 9.1 9.3 Energy Codes and Executive Orders…………………………………….. 9.2 9.4 State and Local Energy Initiatives...……..………………………………. 9.2 9.5 Energy Star and Industry Energy Responsibility Partnerships.……..…… 9.3 9.6 LEED Design and Construction………………………………………….. 9.3 10.0 Solid Waste Management ………………………………………………………. 10-1 10.1 Solid Waste……………..………………..……………………………….. 10.1 10.2 Hazardous Waste………….……………..……………………………….. 10.2 Table of Contents Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 List of Tables Page Table 3.1-1: Existing Land Use within One Mile of White Pine Commerce Park…..… 3.2 Table 3.5-1: Soils………………....………………………………………. Following Chapter 3 Table 3.8-1: Acreage of Vegetation Cover Types………………………..……………. 3.22 Table 3.8-2: Common Species………………….………………………..……………. 3.28 Table 3.8-3: USFWS Endangered and Threatened Species...…………..……………… 3.29 Table 3.11-1: Ambient Noise Data……………..………………………..…………….. 3.37 Table 4.3-1: Trip Generation……..………………………………………..…………… 4.5 Table 4.7-1: Representative Facility Emissions Summary……………………………... 4.20 Table 4.11-1: Typical Construction Equipment Noise Levels………………………….. 4.36 Table 4.11-2: Potential Construction Noise at Receptors……………………………… 4.37 Table 4.11-3: Potential Operational Noise at Receptors……………………………….. 4.39 List of Figures Following Chapter Figure 1.1-1: Project Location …..………………………………………………..…… 1 Figure 1.1-2: Prime Developable Area …..…………………………………………… 1 Figure 3.1-1: Existing Land Use…………………………………………..…………… 3 Figure 3.1-2: Existing Zoning……………………………….……………..………….. 3 Figure 3.4-1: Existing and Proposed Utilities ...…………………………………..…… 3 Figure 3.4-2: Community Services………….…..…………….……………………..… 3 Figure 3.5-1: Topography……….………….…..…………………………………..….. 3 Figure 3.5-2: Soils……….………….…….…..………………………….………..…… 3 Figure 3.6-1: NYSDEC Stream Classifications………..…………………….……..…. 3 Figure 3.6-2: Water Quality Classifications....…..…………………………….………. 3 Figure 3.8-1: Site Wetlands……………………………………………….……….…... 3 Figure 3.8-2: Utility Corridors Wetlands ………………….…………...……………... 3 Figure 3.8-3: Land Cover Types….………………………………..………………….. 3 Figure 3.9-1: Architectural Resources….………………………………..……………. 3 Figure 3.11-1: Sound Level Monitoring and Receptor Locations ….………..……….. 3 Figure 4.11-1: Common Sounds Levels.…………………………..………………….. 4 DGEIS Appendices

Appendix A: SEQRA Documentation and Agency Correspondence

Appendix B: Traffic Analysis Report and Data

Appendix C: Utility Provider Commitment Letters

Appendix D: Visual Impact Assessment

Appendix E: Noise Data

Table of Contents Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021

EXECUTIVE SUMMARY

Project Background Project Location and Description The Onondaga County Industrial Development Agency (“OCIDA”) proposes to expand its modern industrial park at the White Pine Commerce Park (“Park”), formerly known as the Clay Business Park. The Park is located northeast of the intersection of NYS Route 31 and Caughdenoy Road in the Town of Clay, Onondaga County, New York. The Park is approximately 7 miles north of the City of Syracuse.

The Park was created to be capable of supporting a mix of industrial and/or commercial uses with related office space, advanced state-of-the-art research, large- or small-scale manufacturing, assembly, warehousing, data management, material processing and distribution Project Location facilities in a campus-like setting.

OCIDA has devoted substantial time and effort into developing the Park, with a particular focus on development that will bring high-tech facilities and high paying jobs to Onondaga County. More recently OCIDA has focused its efforts on the semiconductor industry. These efforts have been unsuccessful to date as it has become apparent that a larger geographic footprint is necessary in order to support this type of industry and associated investment required by the tenants.

OCIDA, as Project Sponsor, proposes to expand the Park to approximately 1,250± acres (the “Project” or “Action”). OCIDA currently owns approximately 648± acres, has another 282± acres under contract, and would acquire approximately 320± additional acres. The acreage to be acquired are parcels contiguous to the current Park, and are generally located along Route 31, and along the east and west sides of Burnet Road. OCIDA would acquire the additional parcels through purchase agreements with existing landowners or, if necessary, pursuant to the Eminent Domain Procedure Law (“EDPL”), to avoid fragmented parcels that would hinder future development.

Project Overview and History This Draft Supplemental Generic Environmental Impact Statement (“Draft SGEIS”) is a supplement to the 2013 Final Generic Environmental Impact Statement that was completed (“2013 FGEIS”) and OCIDA’s issuance of a Findings Statement that concluded that development of the then existing 340±- acre Park avoided or minimized adverse environmental impacts to the maximum extent practicable, and incorporated mitigation measures that were considered practicable.

P a g e ES 1 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Project Purpose and Need The Project purpose is to expand the Park to enable OCIDA to market the Park to a larger, more diverse mix of potential industrial and commercial developers by making the Project site more attractive to a broader scope of industries, particularly the semiconductor industry, and bringing high tech and high paying jobs to Onondaga County.

This Draft SGEIS identifies, evaluates, and addresses various impact thresholds, permit criteria, and mitigation measures anticipated for the expanded Park, including those attributes associated with large- scale semiconductor industrial development. By addressing these issues in a Generic EIS format, the SEQRA process will define a set of threshold conditions or criteria under which potential future actions and development will be undertaken or approved, including any subsequent SEQRA compliance requirements.

Proposed Development The 2013 FGEIS detailed a preferred development scenario, which anticipated a full build-out of approximately 2.0 to 2.5 million square feet of industrial development and assumed that the Project would be developed in several phases. Given the lack of any specific tenant and uncertain timing for development of future phases, this Draft SGEIS considers the potential impacts associated with the development of the Park, including the expanded area, while providing for further evaluation, as necessary, when a conceptual plan for a specific development is available.

The development evaluated in this Draft SGEIS contemplates OCIDA’s focus on developing the Park with a tenant or tenants in the semiconductor industry. This may translate into a buildout encompassing approximately 4.0 million square feet of industrial development at the Park. This would equate to approximately 400 acres of surface disturbance (temporary and permanent) within the Park developed in a campus like setting that would be sited to avoid regulated wetland areas and would limit the height of structures to no more than 160 feet. This anticipated development is expected to bring approximately 4,000 jobs covering three shifts that operate 24/7 year-round.

Based on a review of similar types of facilities being developed in other areas of the country, and given existing site conditions and the Project purpose, the initial buildout would likely include the following: • A combined total of approximately 4.0 million square feet (SF) of buildings in a campus like setting made up of the type of uses identified in the 2013 FGEIS (manufacturing, laboratory, R&D, fabrication, warehousing, office, support, utility, waste, service yards, energy, water treatment) • Approximately 50 acres of paved area for parking (which may include parking garages), loading, internal road circulation and/or shipping/receiving areas • Two (2) access roads enter the Project site from NYS Route 31 and Caughdenoy Road) • Approximately seven miles of new sanitary sewer line from the Oak Orchard WWTP to service the surrounding sewer district, including the Park • Approximately four miles of new gas line to the Park • Approximately 5,000 linear feet of underground electric line to the Park P a g e ES 2 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 • Areas avoided and set aside for wetland preservation, conservation, and if necessary, mitigation • Additional areas for:

o Stormwater management o Truck scales and security guard stations o Fuel storage o Employee amenities, trails and open space o Landscaping, security fencing, signage, earthen berms and vegetated buffers Project development will include site infrastructure including internal roads, drainage culverts, waterlines, sewer and wastewater systems, electric, natural gas, stormwater management systems, lighting, landscaped areas, earthen berms and areas maintained as undeveloped natural buffers. It is anticipated that areas owned by OCIDA that are north of existing New York Power Authority and National Grid transmission lines will not be developed to avoid actual or potential wetland areas. Upland areas alongside these wetlands may be suitable as possible wetland mitigation areas, if necessary, for potential impacts that cannot be avoided or minimized by a future specific development, which is not covered by this Draft SGEIS.

The development of the Park will likely begin south of the NYPA/National Grid transmission lines to avoid potential wetlands and state wetland adjacent areas to the maximum extent practicable, which are situated in the eastern portion of the Project site. This area includes approximately 732± total acres of prime developable land within the Park. See Figure 1.1-2. This area has been identified as the prime developable area due to the anticipated absence of wetlands features, the generally flat topography, and the access to the surrounding transportation network and potential access points along NYS Route 31 and Caughdenoy Road. The prime developable area within the Project site is also positioned away from the overhead transmission lines, which run across the northern portion of the Project site. The proposed gas line and sewer connection would also tie directly into this portion of the Project site with limited impacts, if any, to wetlands or other natural features anticipated.

Changes in Circumstances The 2013 FGEIS envisioned a Park that would accommodate a mix of industrial uses which could include office, research, manufacturing, assembly, warehousing and distribution facilities in a campus environment. It similarly noted OCIDA’s intent to market the Park “for various types of uses possibly including advanced manufacturing, material processing, product assembly, warehouse and distribution, research and development, and data management to facilitate the creation of high-paying employment opportunities in Onondaga County.” (FGEIS Section 1.2).

OCIDA now seeks to market the Project to a larger, more diverse mix of potential industrial and commercial developers by making the Project site more attractive to a broader scope of industries. The expanded Park will be capable of supporting a mix of industrial and/or commercial uses with related office space, advanced state-of-the-art research, large- or small-scale manufacturing, assembly, warehousing, data management, material processing and distribution facilities in a campus-like setting. As such, OCIDA intends to market the Project site in a more targeted manner to the semiconductor industry. OCIDA would acquire the additional parcels through purchase agreements with existing P a g e ES 3 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 landowners or, if necessary, pursuant to the EDPL, to avoid fragmented parcels that would hinder future development.

Since the completion of 2013 FGEIS, the Climate Leadership and Community Protection Act (CLCPA) was passed and signed into law in 2019 (Chapter 106 of the Laws of 2019). The CLCPA and Environmental Conservation Law (“ECL”) Article 75 require NYSDEC to promulgate regulations to establish a statewide greenhouse gas (“GHG”) emissions limit for 2030 that is sixty percent of 1990 GHG emissions, and for 2050 that is fifteen percent of 1990 GHG emissions. The CLCPA also requires the Public Service Commission (“PSC”) to establish a program to meet a target of seventy percent of statewide electrical generation from renewable sources by 2030, and a target of zero GHG emissions for statewide electrical demand by 2040. NYSDEC adopted 6 NYCRR Part 496 on December 30, 2020, which established the statewide GHG emission limits for 2030 and 2050 consistent with ECL Article 75 and the CLCPA. On October 15, 2020, the PSC issued an Order expanding the Clean Energy Standard to increase renewable energy in the state to 70% by 2030. In addition to the regulations, Section 7(2) of the CLCPA requires all state agencies to consider whether the decision to issue permit(s) is inconsistent with or will interfere with the attainment of the ECL Article 75 GHG emission limits.

Alternatives Several alternatives were fully evaluated in the 2013 FGEIS. This Draft SGEIS updates those that have changed since that time and expands upon others as necessary to account for the proposed expansion of the Park. These alternatives include: no action (Alternative 1); considering the Park as it was originally proposed in the 2013 FGEIS (Alternative 2); utilizing a smaller expanded area – less than the approximately 1,250± acres (Alternative 3); and considering a different location to site the Park (Alternative 4).

Alternative 1 The no action alternative would result in the Park remaining open space and potential habitat for common wildlife that is inaccessible and unutilized by the community until it is sold for other purposes. This alternative would avoid the potential need for to acquire lands pursuant to the Eminent Domain Procedure Law (EDPL) to further expand the lands owned by OCIDA to support future development. See 2013 FGEIS (Draft Section 2.1) for further analysis of this alternative.

The no action alternative would adversely affect Onondaga County’s ability to remain competitive in attracting large-scale industries to Central New York. The no action alternative would preclude potentially beneficial economic impacts associated with the Project, including an increase in employment opportunities and enhanced tax revenues.

Also, current investment in the site may be lost with this alternative, as site conditions change over time. This could decrease the future development potential of the site due to increased costs associated with vegetation clearing and changing drainage characteristics, which may affect the use of additional acreage. The completed technical studies would also be less useful as data and recommendations become increasingly outdated.

P a g e ES 4 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Ultimately, the no action alternative is not an acceptable alternative to the Project, as it is contrary to OCIDA’s mission to facilitate industrial development and job creation in Onondaga County. Alternative 2 Alternative 2 would keep the size of the Park to 340± acres, which is roughly 911± acres smaller than the currently proposed 1,250± acre expanded Project site. Although potential environmental impacts would be limited to a smaller area, impacts on certain resources, such as wildlife may potentially be greater, as sectional development could significantly fragment essential wildlife habitat. The main wildlife mitigation for the Park is to retain/maintain existing habitat tracts, and when not feasible, use compensatory mitigation to include creation or enhanced restoration of habitat to account for any habitat loss. With a smaller park size, it would be difficult to achieve both objectives, including on-site compensatory mitigation due to space limitations. This alternative would avoid the potential need to acquire lands pursuant to EDPL to further expand the lands owned by OCIDA to support future development. A smaller sized Park may not reduce certain environmental impacts such as traffic, visual, air and noise. Instead, it could just reduce the size of open greenspace incorporated into any development design and cause greater wetlands disturbance.

OCIDA has marketed the existing approximately 340±-acre Park since 2013 and determined that the current Park is too small for the type of development it desires to attract to the area and consistent with other industrial park developments in other areas of New York and the country. The smaller, approximate 340± acre footprint would not allow for the potential of larger industrial and commercial developers, such as the semiconductor industry. The proposed expanded footprint of the Park allows OCIDA to market to a larger, more diverse mix of industries than it had previously. The smaller sized Park would not support the main objective, which is to attract a broader scope of industries such as the semiconductor industry, which require a large campus setting with greenspace and ample buffering from environmental receptors and would bring high tech and high paying jobs to Onondaga County.

Although Alternative 2 would avoid the potential need to acquire lands, if necessary, pursuant to the EDPL, it is not a viable option as it would greatly limit the full economic and development potential of the Project site in terms of viable tenants, occupancy and use, and limit options for avoiding and mitigating potential adverse environmental impacts.

Alternative 3 Alternative 3, a smaller expansion alternative, would allow for development on only a portion of the Project site, potentially keeping the remainder of the site in its current state, as vacant, undeveloped land or residential homes, and could reduce, or potentially avoid, the potential need to use EDPL to acquire lands. The smaller expansion alternative would have similar environmental impacts as Alternative 2 (The Park as Considered in the 2013 FGEIS) as well as those described in this Draft SGEIS for the Project. As explained above, the potential for habitat fragmentation on the smaller scale project could potentially cause greater impacts to wildlife. Site development would create additional vehicle traffic in the immediate vicinity and would change the visual character, aesthetics, air and noise quality, vegetation and habitats on-site, regardless of the smaller footprint. It also has the potential to reduce the size of open P a g e ES 5 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 greenspace incorporated into any development design and potentially cause greater wetlands disturbance. The smaller footprint could result in development located closer to residential locations that are not acquired by OCIDA, thus creating greater potential environmental impacts. In contrast, the preferred alternative would allow future tenants additional acreage on-site sufficient to construct necessary buildings and accessory uses, buffer development from adjacent lands, and avoid impacts to ecological resources such as wetlands to the maximum extent practicable.

Although this alternative considers the idea of potentially maximizing development space within a smaller area, much like Alternative 2, the smaller footprint would not allow for the potential of larger industrial and commercial developers, such as the semiconductor industry. The proposed expanded footprint of the Park allows OCIDA to market to a larger, more diverse mix of industries than it had previously. The smaller sized park would not support the main objective, which is to attract a broader scope of industries such as the semiconductor industry that require large campus type settings with greenspace and ample buffering from environmental receptors and would bring high tech and high paying jobs to Onondaga County.

Like Alternative 2, the smaller expansion alternative does not maximize the development potential of the Park and does not expand options for avoiding and mitigating potential adverse environmental impacts. Therefore, it is not an acceptable option.

Alternative 4 Alternative 4 would consist of the development of the proposed Project at a different location. This alternative was previously evaluated and rejected in the 2013 FGEIS (Draft Section 2.2.1). Based on current available information, this conclusion has not changed. None of these previously considered alternative locations would be able to accommodate the large-scale industrial use the Park is promoting due to size limitations and proximity to services and necessary infrastructure. There are no other options available currently that meet the needs of the Project.

Unlike other park locations, the expanded Park can accommodate large-scale industrial tenants that cannot easily locate elsewhere in Onondaga County due to their size and space requirements and need for suitable infrastructure. Additionally, the other locations do not have the existing utility and transportation services that serve the Park. National Grid’s Clay Substation is located adjacent to the Park on the west side of Caughdenoy Road. The Oak Orchard Wastewater Treatment Plant is located approximately 2.5 miles west of the Park. The Park is also bound to the south by a 12-inch water line and NYS Route 31, which is a principal arterial west of Interstate-81, and CSX rail, which is located adjacent to the Park. Based on the lack of other viable locations within the County to accommodate the intended scale of the Park, as well as OCIDA’s substantial investment in the Park to date, this alternative is not a viable option. P a g e ES 6 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Existing Conditions, Impacts and Mitigation Land Use and Zoning The proposed expanded Park footprint consists primarily of undeveloped land. To the extent development exists, it is limited to residential, commercial, and public utility uses and structures (i.e., electric transmission lines, telecommunications tower) scattered along NYS Route 31 and Caughdenoy Road, with approximately three dozen residences located along Burnet Road. Existing improvements and structures within the expanded Park footprint are located close to existing road frontages, leaving the remainder of the expanded Park in its natural, undeveloped state. The majority of the Park is relatively flat and vegetated with grasses, shrub, and wooded areas that have developed as the area continues to transition from former farmland. Land uses within the proposed expanded Park have remained consistent since the 2013 FGEIS.

The area surrounding the Park was once a rural area comprised of farmland and agricultural uses. The surrounding area is undergoing gradual changes as a more suburban type of development unfolds, primarily along NYS Route 31, but much of the area closest to the Park has maintained a rural character due to large swaths of undeveloped land. While farming activities are conducted within a small portion of the proposed expanded Park, the Park is not located within or near a NYS certified agricultural district. The proposed expanded Park is located within the Town of Clay and is subject to the zoning requirements contained in the Town’s Zoning Code and the zoning district designations contained in the Town’s Zoning Map. 1 Of the proposed expanded Park’s approximately 1,250± acres, 346± acres are zoned as Industrial 2 (I-2), 856± acres are zoned Residential Agricultural (RA-100), and 36± acres are zoned One Family Residential (R-15). Burnet Road comprises the remaining 12 ± acres that make up the expanded Park. As shown in Figure 3.1-2 (located at the end of Chapter 3), approximately 850± acres of privately owned land located on Caughdenoy Road west and north of the Park is zoned I-2, with additional parcels zoned RA-100. The parcels directly south of the Park along NYS Route 31 are zoned Highway Commercial (HC-1) and RA-100. The parcel located adjacent to the southeastern corner of the Park is zoned Planned Development (PDD). The proposed expanded Park’s eastern property line is the boundary between the towns of Clay and Cicero. The proposed expanded Park contains multiple zoning designations, not all of which are compatible with the intended future use and development of the Park. The expanded Park will therefore require the approval by the Town of Clay Town Board of either a zone change to I-2 for the portions of the Park that are not zoned I-2 or a PDD that encompasses the entire Park footprint to allow the type of use OCIDA seeks for the Park.

Community Character The Town of Clay is still the largest suburban town in Onondaga County. The Town has a diverse economic base, and industrial uses are scattered throughout the Town, including a developed industrial corridor between Henry Clay Boulevard and Morgan Road approximately 5 miles southwest of the Park. The population of the Town along with its pace of development has remained mostly unchanged since the 1 Town of Clay Zoning Code (Last Revised May 10, 2016). https://www.townofclay.org/information/zoning-code. P a g e ES 7 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 2013 FGEIS. The character of the area immediately surrounding the Park remains generally rural in contrast to the more developed areas of the Town of Clay and nearby Town of Cicero.

NYS Route 31 represents the primary east-west traffic corridor in the Town of Clay north of I-481 and carries a high volume of traffic between Clay and Cicero. Nearly all travel in the vicinity of the project site is by personal vehicle, which remains unchanged since the 2013 FGEIS. There is little public transit and pedestrian use along major roadways, including NYS Route 31, and the area immediately surrounding the proposed expanded Park lacks sidewalks or other pedestrian facilities (crosswalks, etc.) that would otherwise encourage pedestrian use. While NYS Route 31 is a designated part of New York State Bike Route 5, bicycling activity is not typical along the road or surrounding area. The CSX rail line that provides freight service crosses NYS Route 31 southwest of the Park.

Visually, the western portion of the expanded Park contains few structures or natural features of any significance. The topography of the area is generally flat, which is typical of the Town of Clay and the northern portion of Onondaga County. Undeveloped areas contain mixed upland and wetland vegetation including grasses, shrubs, and woodlands. These resources are described in detail later in this chapter under existing ecology and vegetation. The area of the expanded Park that includes Burnet Road contains approximately three dozen residential properties that have been or will be acquired by OCIDA through voluntary purchase agreements or pursuant to the EDPL to help establish the expanded Park footprint. These residential properties will be rezoned to support the proposed development of the Park and existing structures removed from the property.

Electrical utilities, including the National Grid electrical substation located just west of the Park and the NYPA and National Grid transmission lines passing through the northern third of the site are prominent visual features in the area. A telecommunications tower also exists within the expanded Park adjacent to the southeastern corner of the current Park footprint. The presence of these public utility structures and uses incorporates an industrial element to the otherwise undeveloped character of the area. Existing development in the area surrounding the existing Park is either low density single-family suburban style housing or older style rural homes and former farmland. A few business and commercial uses exist along Caughdenoy Road and NYS Route 31 west and south of the Park. With the exception of the area extending north of the Park for several miles that remains largely rural and undeveloped or sparsely developed, surrounding areas in other directions become more densely developed farther away from the Park. Areas east of site along NYS Route 31 and Brewerton Road in the Town of Cicero contain dense concentrations of business and commercial development with residential development interspersed throughout. Higher-density residential and commercial development along the NYS Route 31 corridor within the Town of Clay occurs mostly to the south and southeast of the Park along Stearns Road and Caughdenoy Road north of I-481. Areas farther west of site transition from suburban residential into a developed, high-traffic shopping area along NYS Route 31 around the I-481 interchange. The development of retail, commercial and residential growth farther away from the Park in both directions along NYS Route 31 in Clay and Cicero is due in large part to the proximity of NYS Route 31 to I-81, I- 481, I-90 and the Syracuse Hancock International Airport. Together, those features have made the greater surrounding area attractive to many forms of development.

P a g e ES 8 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 To avoid or minimize potential adverse impacts to the extent practicable, the potential future development of the expanded Park will occur subject to the design features, conditions, and mitigation measures required by the Town of Clay Town and Planning Boards in accordance with the requirements of the Zoning Code. In conjunction with either a zone change or PDD approval process, OCIDA will work with the Town Board and/or Planning Board to identify specific issues or areas of concern and develop specific measures to address or alleviate such concerns to ensure the objectives of the Project are achieved while also minimizing or mitigating development related impacts on the surrounding community. Undeveloped portions of the Park will likely be maintained as wetlands, vegetated greenspace and integrated into stormwater management and other site design features. Additionally, greenspace would be used to meet setback requirements or other design thresholds that may be included in a PDD or site plan. Greenspace may also be incorporated in the tenant facility design/layouts to serve aesthetic purposes, establishing a campus-like setting for tenant employees and visitors.

With respect to the acquisition and removal of residential properties to enable the creation and future development of the expanded Park, OCIDA will negotiate to purchase these properties at fair market value and pay the seller’s normal transaction costs of updating the title and survey, recording fees, transfer taxes and other similar expenses in connection with the transfer of these properties as well as the pro rata portion of real property taxes, water rents, sewer rents, special ad valorem charges and other similar charges. In the event it is necessary to acquire any such properties pursuant to the EDPL, as condemnor OCIDA will offer just compensation based on the fair market value determined by its highest approved appraisal, and the respective property owners will have the right to challenge the amount of such just compensation under EDPL Article 5. OCIDA will also pay, upon acquisition, any costs associated with recording fees, transfer taxes, penalties incurred by the condemnee for prepayment of any preexisting recorded mortgage entered into in good faith encumbering the property, and the pro rata portion of real property taxes, water rents, sewer rents, special ad valorem taxes and other similar charges. Transportation An increase in traffic will result from construction and development of the Park. Traffic is also projected to increase from other developments occurring in the area and will change the existing levels of service (LOS) at certain intersections along NYS Route 31. Therefore, roadway improvements along NYS Route 31 are proposed based on existing and future traffic volumes. Regardless of development at the Park, transportation improvements will be required along NYS Route 31 as other development occurs over time.

Since the preparation of the 2012 Traffic Impact Study that was part of the 2012 DGEIS and finalized in the 2013 FGEIS, traffic roadway changes include:

• The addition of exclusive eastbound and westbound left turn lanes along NYS Route 31 at Henry Clay Boulevard;

• The unsignalized intersections of NYS Route 31/Caughdenoy Road and NYS Route 31/Legionnaire Drive/Lawton Road were signalized;

P a g e ES 9 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 • The Caughdenoy Road/NYS Route 31 intersection was also recommended for right and left turn lane additions; however, the current development assumptions have changed with multiple site entrances.

Impacts related to the proposed expanded Park are described in Section 4.3.

A new Traffic Impact Study (TIS) was prepared to evaluate potential traffic impacts associated with the proposed expanded Park area. Due to the generic nature of this review, the TIS includes more generic as opposed to specific development details and follows the assumptions to develop the traffic impact of the proposed expansion and potential development, which include supporting between 3,750 to 4,000 employees (4,000 used for analysis), having a minimum of two driveways for site access: one driveway will be connected to Caughdenoy Road and the other will be connected to NYS Route 31; operating 24 hours a day and seven days a week with three equally sized rotating working shifts; and development of the Project site will be completed and operational by the year 2024.

Capacity analysis was performed, and the following capacity improvement measures are recommended to address LOS, travel speeds, delay, and safety:

• NYS Route 31 at Henry Clay Boulevard: Construct a northbound left turn lane, • NYS Route 31 at US Route 11: Construct an additional left turn lane to provide for westbound dual left turn lanes and modify left turn phasing from permissive/protected to protected, • NYS Route 31 at I-81 Southbound Ramps: Construct an additional left turn lane to provide westbound double left turn lanes and change westbound left turn phasing from permissive/protected to protected and widen to two lanes on the on-ramp before merging to a single lane prior to the merge on to I-81.

• NYS Route 31 at I-81 Northbound/ Pardee Road: On I-81 northbound off ramp construct an additional left and right turn lane.

• NYS Route 31 at Site Entrance 2: An addition of a left turn lane along NYS Route 31 eastbound and a right turn lane along NYS Route 31 at the site entrance. A left and right turn will be provided out of the site. A traffic signal is recommended at the intersection. • Caughdenoy Road at Site Entrance 1: A right and left turn lane will be provided from the site entrance and along Caughdenoy Road.

• NYS Route 31 at Lakeshore Road: Concepts have been developed and coordination will take place with NYSDOT for future consideration.

Additional information is provided in the TIS in Appendix B.

Utilities & Community Services Existing and proposed utilities (electric, natural gas, and water) in the vicinity of the Park are shown in Figure 3.4-1. Sewer service is in the process of being extended to the surrounding district, including the Park. Gas utility improvements are being proposed in conjunction with the Park expansion. There have P a g e ES 10 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 been no significant changes since 2013 in the location of existing electric, natural gas, and water utilities in the vicinity of the Park.

Community services in the vicinity of the Park include fire, police and emergency response, parks and recreation, schools and other community services such as places of worship. These services remain largely unchanged from 2013. Community service provider locations near the project site are shown in Figure 3.4-2. The area is served by the Clay Fire Department, North Area Volunteer Ambulance Corps (NAVAC), and Northern Onondaga Volunteer Ambulance (NOVA). The Park is in the North Syracuse Central School District which has an enrollment of approximately 8,500 pupils in 2020. The inventory of places of worship in the vicinity of the park is largely unchanged since the 2013 FGEIS was prepared. At least one new church affiliated building, the Upstate New York District Church of the Nazarene, has been built immediately east of the intersection of NYS Route 31 and Burnet Road. The Church uses this

location as its main offices for the Nazarene District. Updated estimates of the potential demands for electric, gas and water supplies, and estimates of sanitary waste volumes have been developed based on the types of industry OCIDA is seeking to attract to the proposed expanded Park:

• Power – up to 500 megavolt-amperes (MVA) • Water – 5 million gallons per day (MGD) • Wastewater – 4 MGD • Natural Gas – up to 7000 meters cubed per hour (m3/hr) OCIDA anticipates that these capacities are adequate to accommodate high technology industries including, but not limited to, semiconductor and semiconductor manufacturing.

Correspondence from National Grid (March 18, 2021, see Appendix C) indicated the existing transmission infrastructure can presently provide up to 540 MVA to the Park, and up to 1,200 MVA is possible in the long term. The estimated Project demand of 500 MVA is within the levels that National Grid has indicated can be provided. No mitigation would be required. No mitigation would be required for fiber optic and phone service which typically expand to meet local demands.

Correspondence from National Grid (March 18, 2021, see Appendix C) indicated that with the extension of the gas main from Gas Regulator Station #147 to the Project site, up to 750 dekatherms per hour (dth/hr) can presently be provided to the Project site with projected future availability of 1,000 dth/hr. The estimated demand of 7,000 m3/hr, equivalent to 245 dth/hr, for potential Park users is within the levels that National Grid has indicated can be provided. No mitigation would be required.

Two routes have been considered to connect the Park to the Gas Regulator Station, a proposed route and an alternative route. See Figure 3.4-1. The location of the proposed route lies within previously disturbed public and utility rights-of-way over much of the length of the proposed route. The alternative route makes use of public rights-of-way for the entire length of the route, but is longer than the proposed route. Permanent and temporary easements would be required along either route. Installation of new gas mains will involve temporary construction impacts along the route. Impacts may include ambient noise, soil P a g e ES 11 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 disturbance, and interruption of traffic at construction access points. These temporary impacts will be mitigated through proper construction and best management practices. Trenching, boring and horizontal directional drilling will be utilized to minimize disruption of traffic during construction and to minimize impacts to any wetlands that may be delineated along the route of the proposed gas line. Best management construction practices will be used, including, soil and erosion control and stormwater management. Disturbed areas will be re-graded and reseeded to pre-construction conditions. Since the proposed route is shorter than the alternative route, construction along the proposed route would result in fewer impacts and it is therefore preferred as the proposed route over the alternative route. According to April 29, 2021 correspondence from OCWEP, the capacity for up to 4.0 MGD is currently available at the Oak Orchard WWTP. The estimated sanitary sewer discharges from potential development of the expanded Park of 4.0 MGD are within the levels that OCWEP has indicated they can accommodate. No mitigation is required. Further OCWEP had previously commenced the design of the conveyance infrastructure to serve lands within the surrounding district and future development areas. OCWEP estimates that conveyance infrastructure will be available within 24 months.

Industrial wastewater pre-treatment may be required on-site by the OCWEP prior to discharge to the Oak Orchard WWTP, if the wastewater strength from the expanded Park exceeds the limits established for discharge to the municipal sanitary sewer system.

The conveyance infrastructure to support developments in the surrounding district including the Park will consist of six-inch and 12-inch diameter PVC force mains. These lines will be located along Caughdenoy Road and in the existing 99-foot wide Metropolitan Water Board easement that parallels NYS Route 31, and the County’s easement that contains the Davis Road Force Main and the Clay – Cicero Force Main to the Oak Orchard WWTP. Installation of new sewer lines will require temporary construction from existing rights-of-way in the area. These temporary impacts will be mitigated through proper construction and best management practices.

Since the majority of the proposed sewer route follows existing MWB and OCWEP easements, the need to procure permanent easements along this route is practically non-existent. However, temporary construction easements required for the installation of bored crossings may be required and to the extent permanent easements are required they will be acquired by OCWEP by negotiated purchase or pursuant to the EDPL. The use of borings under roads and the CSX rail line will minimize disruption of traffic and the need for reconstruction and resurfacing of roadways. Temporary traffic detours may be needed at road crossings.

Trenching will be used through upland areas along the MWB and OCWEP rights-of-way. Most upland areas along the rights-of-way are active cropland or vacant farm fields consisting of shrubs. Best management construction practices will be used in these areas including soil and erosion control and stormwater management. Disturbed areas will be re-graded and reseeded to pre-construction conditions. Wetland mapping shows that federal and state wetlands are potentially present in certain parts of the proposed routes of the utility improvements. Should field surveys verify regulated wetlands are present P a g e ES 12 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 during the course of preparation for utility line construction, the proposed force mains and gas line will be installed through wetland areas using horizontal directional drilling (HDD) methods to avoid adverse impacts.

Public water service is available from adjacent water lines to the Park. According to correspondence from OCWA (March 19, 2021, see Appendix C) indicates that 3,700 gpm at 20-psi is available for the Park. OCWA indicates the current availability for the Park is 1 MGD. OCWA has plans in place that would allow a supply of 5 MGD within 180 days, and potential to provide 11 MGD at an 18 month to two-year horizon. The expanded Park’s estimated water demand of 5 MGD is within the levels OCWA has indicated it can provide, and would not adversely impact the availability or capacity of the local public water supply in the surrounding area. No mitigation would be required.

Future tenants of the Park are expected to provide security and basic emergency preparedness programs for their own facilities. New York State and federal regulatory agencies, such as the EPA, have specific requirements for managing hazardous materials which may be stored on site. Tenants will be required to adhere to all such regulatory requirements. As appropriate based on their industry, tenants of the Park will be expected to have emergency response plans that outline procedures to be undertaken to deal with fire, spills, injuries, etc. Emergency response plans will be reviewed by local officials to ensure that public service providers are properly prepared and equipped in the event they are needed to support tenant security personnel. Tenants are expected to provide on-site water storage for fire suppression and emergency operations. The specifications for fire suppression systems are stipulated in national building and fire codes. The plans for fire suppression and control systems are reviewed and approved by local emergency officials. With the noted life safety, security and emergency response provisions required of future Park tenants, development of the expanded Park is not anticipated to create a burden on the provision of police, fire, and emergency services. No mitigation is required at this time. Development of the Park will not result in the loss of public open space. The extensive regional opportunities for outdoor recreation will easily accommodate the potential increase in population that is brought to the area by employment opportunities in the Park. Potential development of the expanded Park is not anticipated to create adverse impacts on community parks and/or recreation facilities. No mitigation is required.

It is assumed that the future employment opportunities at the Park could bring up to 4,000 new households to the area. New households and primary school students would likely be distributed throughout the Syracuse MSA. The North Syracuse Central School District enrollment would be expected to increase approximately 1.6% (136 additional students to the current district student population of 8,500 pupils). This increase in the student population is not anticipated to place an undue burden or create adverse impacts on local schools and educational services. No mitigation is required. OCIDA intends to acquire the property on which the Upstate New York District Church of the Nazarene is located by negotiated purchase or pursuant to the EDPL and other applicable law. The parcel will become part of the Park and the building will be removed, requiring the Nazarene District office to be relocated. Any community services provided by the church at this location (e.g., counseling, meeting P a g e ES 13 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 space, day care programs, and clothing and food distribution, etc.) would be curtailed by development of the Park.

Topography, Geology, & Soils The topography of the Project Site is generally the same as was detailed in the 2013 FGEIS. The ground is relatively flat to gently sloping, with site elevations ranging from about 380 to 430 feet above mean sea level (amsl). Highest elevations are in the southern portion of the site near NYS Route 31 and the lowest elevations occur in the north part of the site. The site drains to the north towards Youngs Creek, which is a tributary to the Oneida River. Elevation at the expanded Park is most variable along a small ridge located in the central portion of the site. This feature is located approximately 2,000 feet north of NYS Route 31 and generally runs parallel to the road for approximately 3,000 feet. Any potential impacts to topography of the proposed expanded Park would be relatively minor and are consistent with the finding of 2013 FGEIS. No additional mitigation for onsite topographic changes is necessary.

The surficial deposits in the vicinity of the expanded site consist primarily of lacustrine silts and clays deposited in former glacial lakes. These are generally fine-grained and laminated soils. Bedrock beneath the site is mapped as dolostone/limestone, belonging to the Lockport Group. No bedrock outcrops have been noted on the project site. There are no mineral resource extraction areas (gravel pits, mines, quarries, oil/gas wells, etc.) present on the expanded site and the area is seismically stable. Site development will not affect any geologic resources since there are no unique geologic features at the expanded site or in the immediate vicinity. Shallow bedrock is present in some portions of the site and the need for potential blasting during construction and preparation of a blasting plan were discussed in the 2013 FGEIS. No additional mitigation for geologic resources is necessary.

Similar to the park as evaluated in the 2013 FGEIS, the expanded site contains a variety of soils. Based on the physical features of the expanded site, the most likely area for development is west of Burnet Road. In this area, the amount of hydric soils (Cd, FL, and Pb) is approximately 18.7 acres. Hydric soils are characterized by poor drainage. Portions of the expanded site were used for farming in the past. About 40% of the Park soils are considered prime farmland and 9.7% of soils are farmland of statewide importance. Although agriculturally viable soils exist on the site, actual agricultural activity is limited. Most of the expanded site is currently vacant woodlands. Agricultural activities (primarily hayfields) are located at the northern end of Burnet Road. Some cultivated fields also exist in this area. No designated Agricultural Districts exist on the project site and the closest Agricultural District is approximately one- mile northwest (Onondaga County Agricultural Districts, 2019 2). Although the property currently has only limited agricultural use, future development as a business park/manufacturing site will reduce the availability of suitable agricultural soils. This will result in a small, unavoidable impact. Mitigation for soils was detailed in the 2013 FGEIS and no additional mitigation for onsite soil disturbance is necessary. Offsite utility trench construction will require a NYSDEC SPDES permit for construction. This permit will require that erosion control and site restoration measures be established to mitigate any potential impacts to soil.

2 New York State Department of Agriculture and Markets. Onondaga County Agricultural Districts (2019). P a g e ES 14 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Water Resources The Park is relatively flat to gently sloping. Groundwater is expected to flow northward, based upon regional topography and surface water drainage, which is consistent with the Park as it is proposed in the 2013 FGEIS.

The expanded Park is not situated within a primary, principal, or sole source aquifer, although the proposed utility and sewer line routes are partially situated within unconsolidated, confined aquifers. The proposed road improvement to Henry Clay Boulevard is also located within this sand and gravel aquifer. The Park includes several classified streams, including Youngs Creek and several of its tributaries. The proposed gas line connection crosses Shaver Creek and two of its tributaries. The proposed roadway improvements are not expected to comprise of any stream crossings.

There are no FEMA mapped floodplains or Special Flood Hazard Areas within the Park or within the proposed gas line route. The site lies entirely within FEMA flood zone X, which is an area of minimal flood hazard. The preferred sewer line route, however, does have the potential to fall within a mapped FEMA floodplain. Some of the roadway improvements also have the potential to fall within a mapped FEMA floodplain.

Although the Town of Clay and the Town of Cicero are both designated Municipal Separate Storm Sewer Systems (MS4), the site is not located within either of the designated MS4 boundaries. The MS4 boundaries, however, are immediately south and east of the site. As part of the SPDES Construction GP and SWPPP, which is an anticipated requirement of Park development, a MS4 SWPPP Acceptance Form from the Town of Clay and/or Town of Cicero may be required, depending on the off-site locations of the stormwater discharges.

Construction and operational activities at the Park are not expected to have any significant impact to either groundwater and surface water quantity or quality. Furthermore, standard best engineering practices will be employed to minimize any changes to existing topography and vegetative cover which will minimize any related impacts to surface drainage and water quality. As such, no additional mitigation for water resources, beyond what was identified in the 2013 FGEIS is necessary. Air Resources Onondaga County (including the expanded Park area) remains within attainment status of National Ambient Air Quality Standards (NAAQS) for the six criteria pollutants (i.e., ozone, carbon monoxide, nitrogen dioxide, sulfur dioxide, particulate matter, and lead). The NAAQS are levels of pollutants in the ambient air that have been determined to be protective of human health, including the health of sensitive subpopulations such as children, the elderly, and those with chronic respiratory problems; in addition, they are developed to protect public welfare, including damage to property and structures, visibility, vegetation, animal species, and other concerns.

Meteorological conditions for the Syracuse and Central New York region have not materially changed since the 2013 FGEIS. As part of any air permit application submitted to the NYSDEC for development P a g e ES 15 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 of the Park, meteorological conditions will be considered. The closest National Weather Service (NWS) station to the Park that has the appropriate available data for purposes of an air permit application is the Syracuse NWS station, which is located approximately 9 kilometers to the Southeast of the Park. There is a broad international scientific consensus that human activity-generated greenhouse gas (GHG) emissions are increasing the concentration of GHGs in the atmosphere and leading to global climate change. While the contribution to climate change of a single project is very small, the combined GHG emissions from all human activity contributes to global climate change. Regulations and policies have been, and continue to be, implemented to address GHG emissions at global, national, regional, state and local levels. Statutes, policies and regulations that are pertinent to potential development in the Park include New York State’s Climate Leadership and Community Protection Act (“CLCPA”) and regulations under the Clean Air Act. The CLCPA amended the Public Service Law to require the Public Service Commission (“PSC” or “Commission”) to establish a program to meet a target of seventy percent of statewide electrical generation from renewable sources by 2030, and a target of zero GHG emissions for statewide electrical demand by 2040. The regulations and programs to be implemented by NYSDEC and the Commission in accordance with the CLCPA are to be conducted in a manner that minimizes costs and maximizes benefits.

NYSDEC recently adopted 6 NYCRR Part 496, which limits statewide GHG emissions in 2030 and 2050 as a percentage of 1990 emissions, per the requirements of the CLCPA. Part 496 limits statewide GHG emissions in 2030 to 245.87 million metric tons of CO2e, and 61.47 tons in 2050. Part 496 also includes the 20-year global warming potentials for GHGs that are not CO2. The rule applies to all emission sources in New York State, but does not itself impose compliance obligations. The Part 496 statewide emission limits will serve as the baseline for the promulgation of future NYSDEC CLCPA regulations for attainment of the 2030 and 2050 limits. NYSDEC also finalized its Establishing a Value of Carbon Guidelines for Use by State Agencies guidance on December 30, 2020, which is for use by State agencies to monetize benefits/costs of actions that impact GHG emissions based on societal impacts incurred as a result of climate change. CLCPA also requires all state agencies to consider whether its decision to issue permit(s) is inconsistent with or will interfere with the attainment of the statewide GHG emission limits established in ECL Article 75. Where such decisions are deemed to be inconsistent with or will interfere with the attainment of the statewide GHG limits, the agency must provide a detailed statement of justification as to why such limits/criteria may not be met and identify alternatives or GHG mitigation measures to be required where the project is located.

Air quality conditions are influenced by stationary sources and mobile sources of air pollutants. Since 2013, no significant existing stationary sources of air emissions were identified in the vicinity of the Park. The nearest facilities with an air permit are the Buckeye Terminal in Brewerton (approximately 3.3 miles north ) and Barrett Paving Materials in Phoenix (approximately 5.5 miles west). Mobile source emissions are a function of traffic volume and intersection levels of service (LOS). Mobile sources include commuter and truck traffic on NYS Route 31, residential traffic on Caughdenoy Road and other local roads, and occasional emissions from train traffic along the CSX rail line adjacent to the site. P a g e ES 16 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Air emissions resulting from potential development of the proposed expanded Park may be associated with mobile and stationary sources, including transportation vehicles and manufacturing processes, respectively. Potential sources of emissions may be related to manufacturing support systems, heating and cooling, storage tanks, wastewater treatment, and site utilities such as boilers, chillers and back-up generators. Semiconductor manufacturing makes use of processes that require specific chemicals, heat and clean water.

Based on the representative GHG emission estimates for a generic semiconductor manufacturing operation, GHG emissions from the expanded Park could include the following:

• Direct GHG emissions associated with natural gas and fuel oil combustion in boilers, thermal incinerators and other miscellaneous natural gas-fired sources • Carbon dioxide emissions from the oxidation of volatile organic compounds (VOCs) from the expected use of liquid chemicals • Specialty gases used in the manufacturing process, including fluorinated and chlorinated GHGs. • Indirect (upstream) GHG emissions from the import of natural gas and fuel oil Potential direct annual GHG emissions at the expanded Park could range from 150,000 metric tons carbon dioxide equivalent (MTCO2e) to 350,000 MTCO2e. Approximately 10-15% of these GHG emissions are expected to result from the use of specialty gases including nitrogen trifluoride and sulfur hexafluoride, which have 20-year global warming potentials (GWP) of 12,800 and 16,300, respectively. Indirect (upstream) potential annual GHG emissions from the import of fossil fuels could range from 150,000 MTCO2e to 250,000 MTCO2e. For purposes of minimizing GHG emissions, future tenants will be encouraged to promote green infrastructure and energy efficiency (Section 9.0) and, to the extent feasible, use renewable forms of energy to power operations.

As noted in the 2013 FGEIS, all future industrial development will be subject to applicable air emission permitting under NYSDEC. Such an application will be required to be submitted to NYSDEC who will, in turn, review the application in accordance with all applicable state and federal laws, and impose appropriate permit conditions. NYSDEC will also undertake a review of the potential development’s GHG emissions under the CLCPA. Facilities locating within the Park will have to meet air emission permit requirements designed to meet the NAAQS and comply with all applicable regulatory requirements. NYSDEC will impose, as appropriate, permit conditions to implement emission control equipment and other operating parameter and conditions, which any prospective tenant will be required to abide by. In addition to the permitting requirements, mitigation for air pollutant emissions include material handling protocols and industrial good housekeeping practices.

The boilers, incinerator and diesel generators that will be operated at the facility will be new. For the purpose of promoting efficient operation and reducing the potential for excess GHG emissions, these sources will be operated in accordance with the manufacturer’s instructions. Boiler maintenance and testing will also be conducted in accordance with the manufacturer’s instructions. Dual-fired boilers will be operated such that fuel oil will be used as backup and only when natural gas is not available. Some specialty gases that will be used in processes at the facility will have built-in point of use (POU) P a g e ES 17 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 abatement devices which are integral to the processes. POU waste streams are conveyed to the central house scrubbers for further reduction.

With respect to mobile emissions, road and intersection improvements adjacent to the Project site will provide for smoother traffic flow and reduced delays along access roads to the Park. Movement of goods and materials for use by rail will help reduce the amount of truck traffic to and from the Project site. Combined these efforts are expected to generally reduce air emissions associated with potential future development of the Park, including GHG emissions.

Construction-related air quality impacts will be temporary, and mitigation will be implemented to control fugitive dust problems by sweeping and wetting down road surfaces and laydown areas used by haul vehicles. In addition, existing vegetative buffer areas will be maintained to the greatest extent practicable on-site to reduce wind-blown dust. Maintaining vegetated buffer areas and re-vegetating disturbed areas as soon as practicable along the periphery of the Park and internally alongside wetlands and other surface features will help control stormwater runoff and fugitive dust from moving off-site. Erosion and sediment control practices for sediment and dust will be implemented on-site and along utility routes being utilized for the installation of utilities.

Odor Odors can result from emission of organic and inorganic compounds. Different compounds produce different odors and have unique detection and recognition thresholds. Without proper mitigation, the potential exists for odors to occur. As noted in the discussion of air impacts and mitigation, facilities manufacturing semiconductors utilize a variety of controls to reduce the concentration of pollutant emissions.

Ecological Resources Due to the proposed Park expansion, additional mapped wetland areas were identified that were not previously discussed in the 2013 FGEIS. The Park now includes mapped NYSDEC wetland BRE-11, as well as additional mapped NWI wetlands, including NWI wetland classification codes PSS1/EM5C, PUBFH, PFO1C, R5UBH, PUBHx, and PEM5E. These mapped wetland areas are primarily situated on the far eastern and northern portions of the Park. Although NWI mapping indicates the potential presence of federal wetlands regulated by the U.S. Army Corps of Engineers (USACE), the USACE does not publish official wetland maps. These mapped wetlands, including those shown outside of the NYSDEC- mapped boundaries, would also be subject to the recently revised definition of regulated waters under the 2020 federal Navigable Waters Protection Rule, which is narrower in scope and has resulted in an overall lessening of what is considered regulated waters (including federal wetlands) as compared to previous rules and definitions. The definition excludes from the definition of “waters of the United States,” non- adjacent wetlands that do not directly abut or have regular surface water overflow/inundation from intermittent or perennial streams, including wetlands that are adjacent to ephemeral streams, ditches, and prior converted cropland. As such, the extent of regulated wetland areas may be less than shown on the wetland mapping, including those wetland areas discussed in the 2013 FGEIS. Field reconnaissance, and P a g e ES 18 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 if necessary, delineation, based on a conceptual plan for a specific development, will confirm the regulated status of wetland areas potentially impacted, if any.

Land cover types within the expanded Park are mostly consistent with the smaller footprint. Based on review of the NLCD Land Cover data, more than three-fourths of the expanded Park is made up of upland cover types. These communities represent approximately 1,003 acres, up from the approximately 276 acres identified in the 2013 FGEIS, which is approximately 80% of the expanded footprint. As in 2013, there are no critical environmental areas or significant natural communities within or in the vicinity of the project area.

Based on the wildlife species previously observed on the site, potential development at the expanded Park has potential to affect common wildlife species and their associated habitats, although no substantial critical habitat loss is anticipated.

USFWS and NYSDEC/NYNHP identified the following federal- and state-listed threatened and endangered species as having the potential to be impacted by the Project: Sedge wren; Eastern massasauga; and Indiana bat. However, based on the available resources reviewed, there are no threatened and endangered animal species identified by the NYSDEC/NYNHP and USFWS known to inhabit or frequent the Project site. Further confirmation of the absence of these species and habitat at the park would be determined through site reconnaissance once a specific development for the Park is proposed.

Ecological resources, such as wetlands and wildlife habitat would be avoided and minimized to the maximum extent practicable through careful site planning and design. Mitigation is not anticipated if wetland areas are avoided. If a specific development design cannot entirely avoid regulated wetland areas, the Park includes ample space onsite for mitigation wetlands to replace any lost wetland benefits, if necessary.

As there are no anticipated impacts to rare, threatened, or endangered wildlife species or communities, specific mitigation is not required.

Future site development activities, including utility line construction and roadway improvements, however, will be monitored for any occurrence of the identified potential threatened, endangered, or species of special concern, including the Sedge wren, Eastern massasauga, Indiana bat, Osprey, and Sharp-shinned hawk to ensure that construction activities will avoid any direct harm to these listed species. Additional coordination with NYSDEC will also be made prior to the commencement of development activities for concurrence and further guidance, as wildlife/habitat survey(s) may be required (i.e., a grassland breeding bird survey).

Cultural & Archeological Resources The proposed Park expansion contains approximately 1,250± acres of land, much of which was historically used for agriculture. Most of the land is presently cleared, while some is overgrown, and a portion has been used for the Clay-Teall Transmission Line. Burnet Road bisects the property and is lined P a g e ES 19 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 on both sides with an assortment of historic-aged buildings, including residential dwellings and agricultural buildings.

A Phase I Archaeological Survey Report was conducted for the 340± acre Park footprint in 2014 which resulted in a “No Effect” finding on historic properties listed or eligible for listing in the National Register of Historic Places. In response to OCIDA’s lead agency notification letter for the SGEIS, NYSDEC provided that the statewide inventory of archaeological resources records, maintained by the New York State Museum and the New York Office of Parks, Recreation and Historic Preservation, and the expanded Park is not located within a previously designated archeological sensitive area.

Per the New York State Cultural Resource Information System (NYS CRIS), 13 previously identified above-ground historic resources are located within the expanded Park area. Two of these resources are located on the north side of NYS Route 31 and the remaining 11 resources are located along Burnet Road. Seventeen additional previously evaluated resources are located within the immediate vicinity of the expanded Park. Of the 30 previously identified resources, one resource has been determined eligible for listing in the National Register of Historic Places (NRHP) by the New York State Historic Preservation Office (NY SHPO) and 20 have been determined ineligible. The eligibility status of the remaining 9 resources is undetermined.

Residential and agricultural properties constructed prior to 1972 meet the age requirement for consideration for listing in the NRHP. Based on a review of historic aerial photographs, approximately 26 structures which have not been previously evaluated for NRHP eligibility are in the vicinity of the expanded Park and associated utility and roadway corridors. One property on Caughdenoy Road, two on NYS Route 31, and approximately eight properties on Burnet Road contain buildings which appear to have been constructed prior to 1895. Based on historic aerial photographs, most of the remaining historic- age properties appear to have been constructed between 1956 and 1972. The proposed underground utility corridors are primarily located within existing rights-of-way and their construction is not likely to impact above-ground historic resources in the vicinity of the proposed routes.

According to NYS CRIS, the expanded Park is not located within an archaeologically sensitive zone. Small portions of the utility corridors map overlap with archaeologically sensitive zones near previously identified historic-period archaeological sites, but the utility corridors are primarily within previously disturbed areas and rights-of-way.

SHPO is an involved agency and OCIDA will follow the recommendations of SHPO with regard to any further evaluation of cultural and archeological resources within the expanded Park. Should any work be required by SHPO, it will be completed by qualified professionals.

Visual Environment & Aesthetic Resources The Park is presently undeveloped and generally consists of a mix of large upland areas of open field (former agricultural land), shrub and woodland areas interspersed with wet areas. Topography in the area is generally flat to gently sloping. In general, the predominance of vegetation surrounding the site and the relative lack of development contributes to the area’s rural character. This character is influenced by P a g e ES 20 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 former farmsteads, scattered housing along Burnet Road, accessory structures (garages, sheds) and some small business and industrial uses primarily along Caughdenoy Road and NYS Route 31. National Grid’s Clay electrical substation west of the OCIDA site and the transmission towers and high voltage power lines that spread outward from the substation into and across the northern one-third of the site are dominant elements in the local visual environment. The existing CSX rail line also contributes to the somewhat industrial nature of the area. A cell tower located north of NYS Route 31 near the site’s southeastern corner as seen above also influences local views near the site. The relative lack of significant development in the immediate vicinity of the Park, especially views from NYS Route 31 and points east, west, and south of the Route 31 corridor creates the sense of a rural area both during daytime and nighttime periods. Nighttime lighting is generated by existing residential and small businesses as well as by vehicular traffic on local roads. The area does not possess the more suburban characteristics of developed areas located one-half mile or more to the east, west, and south where residential and commercial development has been occurring in recent years.

Distant views of the Park are very limited due to existing stands of woodland and shrub vegetation. The area lacks elevated viewpoints from which the Project can be seen. Most views are therefore highly localized and in general well within one to two miles or less from areas surrounding the Project site. Views of the Park are most significant from Caughdenoy Road and to the east across open fields and farmlands and former farmlands along Burnet Road.

In late 2000, Integrated Site, Landscape Architect, P.C., a consulting firm, conducted a view shed analysis of the Park to determine the potential visual impact of a semiconductor manufacturing plant considered for the Park at that time. Elements of that study and its conclusions remain valid and are discussed in Appendix D.

Due to the expansion of the Park, and the issuance of the 2019 New York State Department of Environmental Conservation’s Program Policy DEP-00-2 “Assessing and Mitigating Visual and Aesthetic Impacts”, an updated Visual Impact Assessment was performed to supplement the original. The updated assessment included a review of previously identified sensitive receptors, identification of new receptors as defined by the 2019 NYS Policy, assessment of views from those locations, and identification of mitigation strategies for potentially impacted locations. The 2019 policy focuses on resources of National, State, and local significance that are open to the public.

The updated Visual Impact Assessment identified a total of 52 sensitive receptor locations that could potentially be impacted by development of the Park. Of those 52 locations, 34 were identified in the previous assessment and 18 were additional locations identified within a 5-mile radius of the Park. Sites determined to have partial or open views to the site will be further assessed as the site development plans are advanced. The developers will work with the county and local agencies during the site development process to identify the best strategies to mitigate any potential visual impacts from the proposed development. Each site will be individually reviewed based upon the site development plans to determine the type and extent of the visual impacts, and to reach consensus on the most appropriate site- specific methods of mitigating those impacts. Based upon the criteria identified in the 2019 NYSDEC Policy, no significant adverse visual impacts to identified public resources are anticipated. P a g e ES 21 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Best management practices implemented during design and construction of the Park will mitigate several visual impacts that could occur with potential industrial development of the Park. More site-specific measures that can be implemented include construction and placement of earthen berms, native plant material, forested buffers, context sensitivity, camouflage/disguise, low profile and consolidation, efficient directional lighting, landscaped site entrances and curved access roads, and integrating mitigation efforts with other site design considerations such as stormwater management areas, safety and security features, fencing, berms, screening walls, building placement, landscaping, etc. No significant adverse visual impacts are anticipated.

Lighting The Project site is predominantly undeveloped, therefore, there is very little light being generated from the site. Light generating sources in the area consist primarily of residences and the cell tower located onsite along NYS Route 31 which has two red warning lights mounted approximately at the mid-point of the tower. These are visible within a quarter mile approaching the tower in both directions. This lighting type, color, and intensity is typically dictated by FAA standards for obstruction marking and lighting. The cell tower will require relocation to an area outside the Park boundary, however, given the relatively close proximity to the Syracuse Hancock International Airport, the new cell tower may require similar lighting. Any facilities potentially established in the Park will require exterior lighting in the form of roadway, parking lot, and building exterior lighting, to provide adequate safety and security for the employees and visitors to the site. The goal of the site lighting plans will be to provide the necessary light levels for safety and security onsite, while avoiding or minimizing glare, reducing light trespass, and reducing skyglow. The lighting design for the site will seek to use Dark Sky friendly lighting fixtures. The lighting design for the approach roadways (NYS Route 31 and Caughdenoy Road) and interior roadways on the site will follow the Illuminating Engineering Society (IES) Recommended Practices for lighting of exterior environments (RP-33-99) and for parking lots (RP-20) to avoid or minimize glare and trespass lighting. The lighting design for the roadways and parking lots will direct light downward using techniques such as cutoff fixtures and shielding. These techniques have proven to be effective in minimizing glare and trespass light that may be detrimental to humans, plants, and animal species surrounding the developed areas of the site and its approach roads. The proposed roadway improvements outside the site will be designed with standard roadway lighting complying with the current NYSDOT HDM Chapter 12 and the NYSDOT Policy on Highway Lighting for highway lighting. Prior to installation of new highway lighting, the locality must agree to be responsible for the operation and maintenance of the new fixture. The luminaire selection for the roadways will be specified according to the IES. The lighting equipment will be selected based on the locality preferences and standards specified in the NYSDOT HDM. Lighting solutions that may create spillover or glare on offsite resources will not be considered for lighting of the roadways.

The site is within five miles of the of the Syracuse Hancock International Airport. This falls within the limits of requirements for obstruction lighting of any onsite structure 200 feet tall or greater. (USDOT FAA Advisory Circular AC70/7460-1M dated 11/16/2020). The development of the site has established a maximum height of 160 feet for any structures built on the site. This would indicate that there will be no P a g e ES 22 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 requirements for Obstruction lighting on the site. Further coordination with the Syracuse Hancock International Airport and the FAA during site design will be required to confirm that no structures erected on the site will require Obstruction Lighting.

Noise The noise impact analysis included impacts from construction and operational activities associated with the proposed expansion of the Park, and also impacts from anticipated roadway improvements. Existing noise in the proposed expanded Park area is generated mostly by vehicular traffic on NYS Route 31 and adjacent roads. Occasional freight trains traveling along the existing CSX rail line near the site, including train signal horns at the existing Caughdenoy Road grade crossing, contribute to the sound environment. Other noise sources in the area include occasional activities such as use of farm tractors and lawn mowing equipment, and wildlife sources typical of a local residential environment. Observed average daytime ambient sound levels in the vicinity of the Park range from 48.0 dB(A) to 73.5 dB(A), with corresponding nighttime ambient sound levels presumed to range from 41.0 dB(A) to 62.9 dB(A).

Receptors potentially sensitive to noise in the project area are generally single- and multi-family residential homes along Caughdenoy Road, NYS Route 31, Verplank Road, and surrounding roadways. Highly sensitive receptors such as schools, libraries, hospitals, and parklands do not exist near the Park, although two local parks are located to the west and southeast along NYS Route 31.

Based on a potential development and a conceptual footprint over the prime developable area, a noise impact assessment finds that:

• Operation of the Park is not anticipated to increase sound levels above current daytime levels at surrounding property lines or sensitive receptors.

• Operation of the Park may increase sound levels above current nighttime levels at surrounding property lines or sensitive receptors by up to 4.4 decibels. Per NYSDEC guidance, sound level increases of this magnitude are considered “unnoticed to tolerable,” and present the potential for adverse impacts only in cases of the most sensitive receptors • Temporary and intermittent construction activities at nearby receptor property lines has the potential to increase sound levels by more than 10 decibels.

Site layout, operations schedules, natural buffers, vegetative screening, and earthen berms or engineered sound barriers can be employed to mitigate potential noise impacts. At a minimum, the following mitigation measures will be incorporated into the various phases of site development to reduce potential noise impacts.

• Community accessible information including construction schedules will be prepared by project tenants and made available at suitable locations (door-to-door, websites, town offices) to notify neighbors of upcoming work. A complaint resolution process will be implemented and monitored by the tenant and/or OCIDA during construction.

• All construction equipment will be maintained with properly functioning noise reduction muffler systems per manufacturer’s specifications as part of construction contracts and contractor responsibilities.

P a g e ES 23 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 • Earth-moving equipment will be restricted from “tail gate banging” during sensitive times of the day (early morning and late evening) and when operating near residential receptors. • Building construction near adjacent residential receptors will consider phasing opportunities and scheduling work to reduce potential noise impacts by erecting buildings, berms, stockpiling materials, structure placement, etc. to interrupt sight lines and therefore reduce noise levels being generated in the direction of sensitive receptors as construction advances on-site.

• Haul roads, access drives, materials storage areas, staging areas, etc. will be placed as far from sensitive receptors and internal to central portions of the site to the greatest extent practicable.

• Limiting construction to normal daylight hours to the greatest extent practicable. If nighttime construction is required, consideration will need to be given to use of variable level audible back-up alarms on heavy equipment, and/or use of strobe lights or other OSHA approved safety devices.

• Establish a project hotline (website and phone numbers) so residents can be kept informed of the status of project construction and obtain information for forwarding on complaints relative to construction activity due to noise, dust, work hours, etc.

Human Health Human health considerations address potentially sensitive receptors in proximity to a project. The proposed expansion of the Park is within 1,500 feet of the recently built Cottages at Garden Grove Nursing home. This facility is approximately 200 feet east of the eastern site boundary. Grace Evangelical Covenant Church is also located just south of the site along NYS Route 31. The church, which has after- school programs for children, is located just west of Burnet Road and about 2,500 feet west of a possible NYS Route 31 entrance to the expanded Park.

Due to the anticipated construction and operations of the expanded Park, there could be activities that cause some degree of change to the physical aspects of the surrounding area, including the potential for increased traffic, air emissions and noise. These changes have the potential to cause small to moderate impacts to the human health of surrounding residents including the sensitive receptors identified above. Minimization and mitigation for temporary impacts during construction activities include restrictions on site access, hours of construction activity, delivery of equipment and materials to the site, measures to control dust from disturbed soil, best management practices for temporary fuel storage, and flagging/traffic control measures to protect all modes of travel within any construction area or public right-of-way. During future operations, general impact minimization and mitigation measures will require that the future site tenants obtain all necessary local, state, and federal permits, demonstrating that they are developing and operating the site in accordance with all regulatory requirements and laws. Mitigation measures for potential impacts related to traffic, air quality and noise will include improvements in intersection designs, implementation of air emission control devices, compliance with air emission limits, and use of vegetative/earthen noise barriers between new facilities and neighboring properties. P a g e ES 24 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Cumulative Impacts It is anticipated that the expansion of the Park and future development of the Park for industrial semiconductor manufacturing will induce similar cumulative impacts and effects to the area as were identified in the 2013 FGEIS. It remains possible that the expanded Park could be a catalyst to additional industrial and business development in this area. Particularly, the area to the west of the Park along Caughdenoy Road that is already zoned for industrial uses (I-2). The addition of the sewer line to and through this area further adds to the attractiveness to develop this area for industrial or business use. There are several new developments in various stages of approval and review by the Town of Clay Planning Board. The two most relevant developments are a 60-unit senior housing complex along Brewerton Road east of the Park, which was recently approved by the Town of Clay Planning Board for construction. There is also a mixed use Planned Development District (PDD) on the corner of NYS Route 31 and Henry Clay Boulevard that will soon be presented to the Town of Clay Planning Board for approval. If approved, this new PDD will include approximately 100 ± apartments and some mixed-use retail units on the bottom floors towards the front of the parcel. It is not anticipated that the construction of either of these potential developments would create cumulative impacts if constructed concurrently with the development of the Park.

The development of the expanded Park or any surrounding areas that develop as a result of development at the Park could create positive cumulative impacts and economic spin-off. This could include an increase in employment opportunities, increases in local discretionary spending providing additional sales tax revenues to State and local governments, demand for new goods and services support businesses, and further diversify the tax base of the Town of Clay.

The installation of sewer force main along NYS Route 31/Caughdenoy Road intersection and northward along Caughdenoy Road paired with the various intersection improvements along NYS Route 31 will likely make this area attractive to industrial and business uses as well. Added industrial and business uses would increase traffic along NYS Route 31 and Caughdenoy Road. The additional traffic on NYS Route 31 could impact levels of service at several intersections and require improvements at a quicker pace than presently expected as discussed in Chapter 4 Section 4.3.

Potential new growth and economic expansion could create some adverse cumulative impacts. Changes in surrounding land use could put additional demand on sewer capacity and wastewater treatment at the Oak Orchard WWTP and may require upgrades to capacity at the plant to support future growth in the area. The conversion of undeveloped land to other uses will cause a loss of vegetation and wildlife habitat. Encroachment and impacts to features including but not limited to wetlands and floodplains may occur. Changes in visual character from relatively undeveloped land to increased densities may also result. Depending on the nature and extent of development, there may be increased demand on municipal services for fire, police and emergency services. There may also be increased demand on housing, schools and local utilities. The mitigation of these potential impacts will need to be determined as new development projects are introduced and will need to be coordinated at that time with the Town of Clay and possibly other entities and Involved Agencies.

P a g e ES 25 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Road improvements, the provision of infrastructure, particularly expanded sanitary sewer capacity at the Oak Orchard Wastewater Treatment Plant, and the potential cost implications for increased municipal services in anticipation of further development of the area would require local, State and federal funding. The establishment and implementation of policies at the Town and County level will be required to manage land use and infrastructure development along and especially north of the NYS Route 31 corridor to control the potential for adverse effects of additional development in the area. These policies may be established through the Town of Clay Northern Land Use Study and/or the Onondaga County Comprehensive Plan update. Implementation could also be accomplished through Town zoning and County Section 239 project reviews.

Unavoidable Adverse Impacts Many of the unavoidable adverse impacts that are likely to result from the expansion of the Park remain similar to those anticipated during the 2013 FGEIS. The difference is the geographic extent given the proposed Park expansion, which could result in greater impacts but also allow for additional buffers to avoid, minimize, and mitigate certain impacts (e.g., ecological, noise, etc.). The unavoidable impacts include the following.

Construction Impacts It is expected that the expansion of the Park and subsequent construction activities during the development of the Park will generate some temporary impacts as an unavoidable consequence of the development of the Park. These impacts and their intensity will vary throughout the phase one development of the Park. Impacts are likely to include an increase in truck traffic on nearby roads, primarily NYS Route 31 and Caughdenoy Road as construction workers and materials are transported to and from the Project site.

As identified in the 2013 FGEIS, heavy machinery and construction equipment will be used throughout construction. As a result, noise levels will increase in surrounding areas during construction activity. Limiting the placement and storage of equipment and materials as far as possible from residences surrounding the Park will help to mitigate the increase in noise levels. Construction activities will also be limited to normal daytime hours whenever possible consistent with the Town of Clay Noise Ordinance requirements to minimize impacts to nearby residents.

Excavation and the transport of materials have the potential to create fugitive dust from unpaved surfaces depending on wind direction and drying conditions. Dust will be controlled by sweeping adjacent roads to the Project site and watering access roads on site as needed. In addition, in compliance with State water quality and stormwater management regulations future development will require a complete detailed Erosion and Sediment Control and Stormwater Pollution Prevention Plan prior to any construction. These plans will be developed by future project tenants in compliance with all local, State and federal regulations. Contractors working on site will also be required to follow best management construction practices to reduce the potential for soil erosion, dust, noise, traffic and other construction impacts. P a g e ES 26 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Traffic An increase in traffic will result from construction and development of the expanded Park. Traffic is also projected to increase from other developments occurring in the area and will change the existing levels of service at certain intersections along NYS Route 31. Therefore, roadway improvements along NYS Route 31 are proposed based on existing and future traffic volumes. Regardless of development at the Park, transportation improvements will be required along NYS Route 31 as other development occurs over time.

Air Quality and Noise Future industrial use at the expanded Park will result in increased traffic, including employee vehicles, trucks, and the possible use of rail. This will increase noise and air emissions from the Park area. There will also be an increased use of energy, water and wastewater treatment resulting from development, but the exact degree of increase is unknown at this time. The use of natural gas for process heat demands and thermal oxidizers for the destruction of volatile organic compounds will generate combustion related air pollutants. The use of chemicals in manufacturing processes will generate non-combustion air pollutants. Emission control equipment will be utilized to reduce the emission rates and overall volume of released pollutants.

Ecology Areas of open field cover type within the Park will be developed. It is anticipated additional upland shrubland and woodland habitat areas will also be affected. Impacts to state and federal jurisdictional wetlands will be avoided to the maximum extent practicable, but to the extent a specific development project cannot entirely avoid or minimize impacts to wetlands, associated habitat areas may also be impacted by development of the Park. This is consistent with the findings of the 2013 FGEIS. Much of the Park will maintain its natural habitats as areas set aside from development. Some areas on site that may experience temporary disturbance from construction activities could return to vegetated locations (i.e., stormwater management areas, landscaping, and visual buffers). As such, suitable wildlife habitat will be present in the Park in areas avoided by development or that are restored following construction. Visual Character Similar to the analysis in the 2013 FGEIS, the development of the expanded Park site will alter the visual character, which currently consists of single family rural residential plots, undeveloped rural open space comprised of former farm fields, and shrub and woodland. The future development at the expanded Park will instead include industrial buildings, parking areas, support facilities, and internal roads. It is anticipated that during the development at the expanded Park the wetlands within the Park will remain undeveloped.

Visual changes resulting from construction and development are unavoidable. Measures to reduce the effects of visual changes include the placement of additional vegetative buffers and landscaped berms at key locations around the site, particularly along the western and southern periphery of the site to screen views and mitigate noise.

P a g e ES 27 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 The need for specific visual mitigation measures will be determined once tenants are known and the degree of potential visual impact is determined. Building placement, the use of attractive building materials and structural design features and landscaping will be encouraged by OCIDA to enhance the appearance of buildings and grounds. Appropriate lighting fixtures and other site design features will be determined in coordination with the Town of Clay’s site plan review process.

Displacement of Existing Property Owners In order for Project objectives to be achieved, OCIDA must increase the size of the Park to make it more attractive to potential future tenants, specifically tenants in the semiconductor industry. The proposed expanded Park footprint requires that OCIDA acquire certain residences along Caughdenoy Road, NYS Route 31 and approximately 3 dozen residences along Burnet Road. These residential properties have been acquired or will be acquired by OCIDA through negotiated purchase agreements or pursuant to the EDPL and existing owners will need to relocate. OCIDA must also acquire the property on which the existing telecommunication tower is located.

The properties along NYS Route 31 and Burnet Road represent a significant portion of the expanded Park’s prime developable area and are therefore a necessary component of the Project. Existing structures and improvements will ultimately be demolished and/or removed in furtherance of the potential future development of the Park. Demolition activities will be conducted in accordance with Town of Clay requirements, and all debris will be disposed of at authorized off site facilities in accordance with applicable regulations. The telecommunications tower will need to be disassembled and relocated. The acquisition and removal of the residences along Burnet Road allows for the expansion of the Park footprint to accommodate large-scale campus like development for tenants and will enable maximum use of setbacks and buffers between the prime developable area of the Park and the nearest land uses to the east along and off of Brewerton Road in the Town of Cicero.

While the removal of the aforementioned residences and tower are unavoidable, owners will receive fair market value for their properties, thus enabling them to relocate within the Town of Clay or elsewhere. OCIDA will also pay the seller’s normal transaction costs of updating the title and survey, recording fees, transfer taxes and other similar expenses in connection with the transfer of these properties as well as the pro rata portion of real property taxes, water rents, sewer rents, special ad valorem charges and other similar charges. In the event it is necessary to acquire any such properties pursuant to the EDPL, as condemnor, the Agency will offer just compensation based on the fair market value determined by its highest approved appraisal, and the respective property owners will have the right to challenge the amount of such just compensation under EDPL Article 5. The Agency will also pay, upon acquisition, any costs associated with recording fees, transfer taxes, penalties incurred by the condemnee for prepayment of any preexisting recorded mortgage entered into in good faith encumbering the property, and the pro rata portion of real property taxes, water rents, sewer rents, special ad valorem taxes and other similar charges.

P a g e ES 28 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Growth-Inducing Impacts The growth-inducing impacts that are likely to result from the expansion of the Park remain similar to those anticipated during the 2013 FGEIS.

Population Growth It remains reasonable to expect that the development of the expanded Park will result in some direct and secondary growth impacts to the surrounding community. Direct impacts will result from the development of the Park itself. Secondary impacts such as industrial-related support businesses or other commercial businesses being established near the Park are also possible.

Direct impacts will include job creation both on a temporary basis during construction and long-term employment once buildings and ancillary facilities are completed and become operational. It is anticipated that construction of a campus for large semiconductor industrial tenant will occur over the course of a year or more.

Most job opportunities created during construction will be filled by the local labor pool. However, it is anticipated that the development of the expanded Park will bring approximately 4,000 full-time high paying jobs to Onondaga County. The potential exists for many of these new jobs to be filled by people that are not currently living within the Syracuse Metropolitan Area, meaning that there could be a proportional increase in the number of households as well as the need for new housing. It is estimated that the North Syracuse Central School District enrollment would increase by approximately 1.6%. This increase in school population is not anticipated to place an undue burden on local schools and educational facilities, mainly due to the recent decline in the Syracuse Metropolitan Area population and resulting decline in the student aged population.

Infrastructure-Induced Growth The development of the expanded Park will necessitate the construction of new infrastructure. The most important infrastructure improvements that are needed to support the proposed development include the traffic mitigation improvements described in Section 4.1.10, the installation of sewer force mains being designed to support the greater Oak Orchard District and a gas line as described in Chapter 3 and 4, Sections 3.4.1 and 4.4.1, respectively.

Utility connections on-site will not result in substantial growth-inducing impacts since its effects will be in support of on-site uses, but these new utilities could encourage some new growth along their conveyance routes. The availability of public sewer has the potential to foster additional development in this portion of the Town of Clay, which remains relatively undeveloped at the present time. The ability to tap into the force mains is subject to State, County and Town of Clay review and approvals. As such development will be managed by these entities and by the available capacity of wastewater treatment at the Oak Orchard Treatment Plant. Formation of a new sewer district to serve the Clay Business Park could help manage growth in the area. The County can service up to 4 million gallons per day (MGD) at Oak Orchard for the Park.

P a g e ES 29 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Transportation improvements along the NYS Route 31 corridor could also accelerate and accommodate increased development activity. Traffic improvements will be required along NYS Route 31 as development occurs. Traffic mitigation improvements proposed to support the expanded Park are not likely to induce further growth alone without other improvements along the corridor.

Development in the vicinity of the expanded Park could take several different forms at varying scales and densities depending on real estate market conditions and trends when new sewers come online. It is expected that future development in the vicinity of the Park will be in accordance with the Town of Clay Zoning Code and any related regulations or requirements in effect at the time. Under current zoning, this could translate into additional industrial development west of Caughdenoy Road and along NYS Route 31.

Development of residential uses could also occur in the vicinity of the Park as the result of sewer availability. Residential uses, perhaps as new residential subdivisions along NYS Route 31 south and east of the Project site may occur in areas presently zoned as RA-100.

All new development that occurs off-site will be subject to Town of Clay zoning requirements and site plan review. Such projects will also be subject to an environmental review under SEQRA conducted by the Town and/or other Involved Agencies at the time a specific project is proposed. Potential adverse environmental impacts will be identified, evaluated, and subject to project-specific mitigation measures on a case-by-case basis as part of the SEQRA review process.

Irreversible and Irretrievable Commitment of Resources Similar to the 2013 FGEIS, it is anticipated that the expansion of the Park and subsequent development of the Park will require similar commitments of various types of community resources by OCIDA, Onondaga County and other entities including the private sector as investment and development of the Park progresses.

The irreversible commitment of physical resources will include the conversion of approximately 4.0 million square feet of the expanded Park to building footprint and additional support facilities in support of industrial semiconductor uses. There will also be 50± acres of parking (which may include parking garages), loading areas, access and internal circulation roads at the expanded Park.

As evaluated in the 2013 FGEIS, the prime developable area of the Park generally consists of fields, shrubland, and some woodland areas. Residential properties may now be part of the prime developable area given the proposed expanded footprint of the Park along Burnet Road. Also similar to the 2013 FGEIS, areas that are likely to remain mainly undeveloped generally consist of wooded upland, wetlands and NYSDEC wetland buffer areas.

As analyzed in the 2013 FGEIS, development of the Park will require soil disturbance as well as the loss of vegetation and wildlife habitats. However, the goal will be to avoid wetlands and mature habitats to the maximum extent practicable by focusing development in the prime developable area. Topsoil will be stockpiled for use on-site for landscaping, whenever possible. Trees removed for development will be P a g e ES 30 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 considered for sale as timber and other vegetation cleared from the Project site will be recycled as mulch and landscaping, when practicable. The only difference from 2013 may be the amount of soil disturbance and trees impacts from development given the proposed expansion and greater Park acreage. Development will include the commitment and consumption of building and construction materials including concrete, asphalt, steel, lumber, plastics and other raw materials and finished products. Development will require the consumption of water, electricity, fuel (gas and diesel), oil and other petroleum products. Additional materials and energy resources will be consumed by tenants for industrial processes. The provision of utilities for water, sewer, electrical, natural gas, and telecommunications will be required throughout construction and operation of facilities. The use of materials and goods are expected to be met by the region’s supply. Nevertheless, as in 2013, this represents an irreversible and irretrievable commitment of these resources that will not be available for other uses. The proposed Action will also require public and private services, including, but not limited to, solid waste disposal, police, fire and emergency services, as expected with any large-scale development and as detailed in the 2013 FGEIS. Commitment of these resources is an anticipated outcome of an industrial park’s development.

Effect on the Use and Conservation of Energy Resources Commitment and indication of adequate capacity from National Grid to support the expanded White Pine Commerce Park with Natural Gas and Electric utility service was received. The expanded Project Site is capable of supporting a mix of industrial and/or commercial use facilities located in a campus-like setting. The facilities will consume natural gas and electricity as a result of normal operations. It is anticipated that approximately 25 acres of the site could be used for a potential electrical substation and gas regulator station to support the energy needs of the expanded project site. This space has potential to be a central energy facility intended for energy distribution to the campus facilities and buildings while minimizing the quantity of equipment needed and maximizing energy efficiency. The expanded Park may employ up to 4,000 employees and operate up to 4 million square feet of facilities. Potential facilities include the following use types:

• manufacturing/fabrication/assembly space • laboratory, research and development (R&D) space • logistics, warehousing, and/or shipping & receiving space • office and administration space • manufacturing support facilities, outdoor utility spaces, maintenance areas, waste facilities, and service/storage yards • on-site energy generation or electrical substation space • wastewater treatment systems or pump stations • paved area for parking (which may include parking garages), loading, internal road circulation and/or shipping/receiving areas P a g e ES 31 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Although the objective of expanded Park is to develop the site for the semiconductor and manufacturing industry, the actual demand for energy can vary greatly according to the types of industries and businesses eventually located in the Park.

US Energy Information Administration’s (EIA) 2018 Manufacturing Energy Consumption Survey identified that manufacturing facilities, on average, consume 95.1 kilowatt-hours (kWh) of electricity and 536,500 British thermal units (Btu) of natural gas per square foot annually. This average can increase or decrease significantly depending on the facility use type, manufactured product, and manufacturing process.

Buildings and uses designed for the expanded Park will be constructed utilizing equipment and systems in compliance with energy conservation and building code standards as set forth by New York State Construction Codes. New York State has several codes and NYS programs related to their building energy code. These include the State Energy Conservation Construction Code (SECCC), the NYS Executive Order No. 111, and The New York Energy Smart Program.

The SECCC determines the minimum energy conservation requirements for new buildings including heating and ventilating, lighting, water heating, and power usage for appliances and building systems. Specific design requirements are related to the climate zone the building is located (Onondaga County, Zone 5A). Low energy and equipment buildings are exempt from the building thermal envelope provisions.

The NYS Executive Order No. 111 provides the guidelines for energy use and environmental issues for New York State buildings and vehicles. While this Executive Order would not apply to Private Industry, it represents an Energy Conservation Model recognized within the state that can be referenced by private industry. Some of the goals are to increase the availability of renewable energy sources and premium efficiency products, reducing peak summer energy demand and creating a less oil dependent economy. For new construction equal to or greater than 20,000 gross square feet, the building must achieve at least a 20% improvement in energy efficiency performance, meet the criteria for a U.S. Green Building Council Leadership in Energy and Environmental Design (LEED) rating, and comply with the New York State Green Building Tax Credit requirements.

The following incentives are available to industry within NYS with a clear intent to promote and reward the use of energy efficient systems and policies. Several are available to industry located within Onondaga County and are promoted and coordinated by OCIDA. It is in the best interest of any industry locating at the expanded Park to be as energy efficient as possible to control operating costs as well as contribute to achievement of NYS initiatives and energy objectives. New facilities systems are expected to be designed to be highly energy efficient using the latest technologies in energy use and conservation which represent the most cost effective and responsible approach for the industry.

OCIDA coordinates incentive packages for businesses through the New York State Energy Research and Development Authority (NYSERDA) commercial/industrial programs. These programs provide energy efficiency services for new construction, industrial facilities and vehicle fleets. NYSERDA services P a g e ES 32 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 include new renewable, clean energy and energy efficient product manufacturing incentives and services designed to promote greater transportation, lighting and HVAC efficiencies.

Energy Star is a voluntary partnership program of the U.S. Environmental Protection Agency (EPA). Its primary purpose is to help U.S. industry improve its competitiveness through increased energy efficiency and reduced environmental impact. Through Energy Star, the U.S. EPA encourages strong and strategic corporate energy management programs and provides energy management tools and strategies to assist companies implement such programs. There are several methods for designers, contractors, and building managers to be recognized by the EPA. The most notable is the Energy Star Building Certification which requires the building to meet strict energy performance standards set by EPA. These standards include energy performance indicators (EPIs) to calculate energy intensity and to score the facility on a 1-100 scale. A score of 75 or above is required for certification, but certification is not available for all building types and for all sectors of industry. For a building in the design phase, there is the Designed to Earn Energy Star Recognition, which signifies that the operating energy use of the building is designed to be in the top 25 percent as compared to similar buildings throughout the U.S. Industrial and manufacturing facilities that are not part of EPA’s Industries of Focus are eligible to participate and receive Energy Star’s Challenge for Industry Recognition which is designed to help energy managers and industrial sites improve energy performance and set goals. Industrial sites participate by committing to the pre- established goal of improving energy performance by 10 percent within 5 years or less. Currently, semiconductor manufacturing, including, but not limited to wafer fabrication and processing, is not eligible for an Energy Star Building Certification, but can be recognized through both the Designed to Earn Energy Star Recognition and Challenge for Industry Recognition. These programs offer advanced tools to assist manufacturers in assessing and tracking energy use and prescribing energy management and improvement initiatives with goals of energy reduction. Achievement of set energy reduction and environmental improvement goals results in receiving recognition.

Unstable energy markets, increasing competition, and global regulation of greenhouse gas emissions are currently causing many U.S. manufacturers to implement energy management as a viable opportunity. A reduction in production cost can be achieved without negatively affecting the yield and quality of products by effectively reducing energy consumption and costs. This goal can often be met through investments in energy efficiency, which can include the implementation of plant-wide energy-efficiency practices and the purchase of energy-efficient technologies. These technologies can often offer additional benefits, such as quality improvement, increased production, and increased process efficiency. OCIDA promotes State and Federal incentives to encourage users to develop the Park with energy systems that are both energy efficient and environmentally friendly. This can be accomplished through the planning, design and construction of facilities that are consistent with Leadership in Energy and Environmental Design (LEED) certification standards. Standards include energy efficient heating, ventilation and air conditioning (HVAC) systems, and day-lighting of interior spaces.

P a g e ES 33 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 Solid Waste Management As a result of the proposed Park expansion, there is a potential for increased generation of solid and hazardous wastes, which represents a change from what was considered in the 2013 FGEIS. The impact will not be significant in terms of total service area and capacity. It is anticipated that local haulers will provide adequate services to the Park, as is currently being provided to other businesses and industrial users in the County. No additional mitigation is necessary since potential impacts due to solid waste generation are minimal.

OCIDA will work with any future tenants to develop a solid waste management program that includes recycling and reuse of materials. Management and disposal of solid waste will be consistent with the goals established by the Onondaga County Resource Recovery Agency (OCRRA) in its September 2016 Solid Waste Management Plan Update. It is anticipated that a Project site developer will institute measures to reduce solid waste generation, reuse materials (where possible), and institute recycling measures. These “best-management” practices are cost-effective alternatives to offsite disposal. Transportation and disposal of non-hazardous solid waste will be coordinated with a licensed solid waste hauling firm. It is anticipated that material will primarily be taken to OCRRA’s Waste to Energy Facility in Jamesville or an approved transfer station. OCRRA also has contingency plans for disposal of waste, if necessary, at facilities such as Seneca Meadows Landfill (Seneca County) or High Acres Landfill (Monroe County). Future development and operations within the Park will be required to comply with Chapter 194 of the Town’s Solid Waste Code.

Manufacturing activities at the expanded Park could include the use and storage of petroleum, compressed specialty gases, and chemicals such as paints, solvents, chlorine, corrosive materials, and materials contaminated with metals. Specialty gases that may be used or generated by a prospective tenant could include nitrogen, nitrogen trifluoride, oxygen, carbon dioxide, silane, nitrous oxide, helium, and argon. Various types of hazardous waste may be produced as a result of the potential manufacturing activities that could take place at the expanded site. It is possible that up to approximately 60,000 tons of hazardous waste could be generated per year. Hazardous waste could be in solid, liquid or gaseous forms and is considered hazardous because of its physical characteristics or the process that generated the waste. Potential waste streams may include solvent wastes, isopropyl alcohol, acids, hydrogen fluoride, ethylene glycol, chlorine, wastewater sludge, metal slurries, and metal plating wastes. Hazardous waste that is generated, treated, and stored is controlled by permits and regulations administered by NYSDEC and USEPA, under the Resource Conservation and Recovery Act (RCRA). Off-site disposal of hazardous waste would be coordinated with a licensed hazardous waste hauler and one or more permitted treatment/disposal facilities. Permitted facilities in New York State that accept hazardous waste include Chemical Waste Management - Model City (Niagara County) and Durez Corporation (Niagara County). Alternatively, hazardous waste may be transported out-of-state using private vendors.

Various types of hazardous materials may be produced a result of the potential manufacturing activities that could take place at the proposed expanded Park Generation of waste products has the potential to create a small to moderate impact if not handled properly and in accordance with State and Federal regulations. However, any such impacts will be mitigated through the use of engineering controls, staff P a g e ES 34 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 training, best-management practices, and regulatory compliance with State/Federal permits, laws and regulations will be instituted.

P a g e ES 35 Executive Summary Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021

1.1.1 Project Description

The Onondaga County Industrial Development Agency (OCIDA) proposes to expand its existing White Pine Commerce Park (“Park”), formerly known as the Clay Business Park. The Park is located northeast of the intersection of NYS Route 31 and CR 49 (Caughdenoy Road) in the Town of Clay, Onondaga County, New York. It was created to be capable of supporting a mix of industrial and/or commercial uses with related office space, advanced state-of-the-art research, large- or small-scale manufacturing, assembly, warehousing, data management, material processing and distribution facilities in a campus-like setting.

OCIDA has devoted substantial time and effort into determining the highest and best use of the Park, with a particular focus on site attributes that will bring high-tech facilities and high paying jobs to Onondaga County. More recently OCIDA has focused its efforts on the semiconductor industry. These efforts have been unsuccessful to date as it has become apparent that a larger geographic footprint is necessary in order to support this type of industry and the associated investment required by the tenant(s). OCIDA, as Project Sponsor, proposes to expand the Park to approximately 1,250± acres (the “Project” or “Action”). OCIDA currently owns approximately 648± acres, has another 282± acres under contract, and would acquire approximately 320± additional acres. The acreage to be acquired are parcels contiguous to the current Park, and are generally located along Route 31, and along the east and west sides of Burnet Road. OCIDA would acquire the additional parcels through purchase agreements with existing landowners or, if necessary, pursuant to the Eminent Domain Procedure Law (“EDPL”), to avoid fragmented parcels that would hinder future development.

1.1.2 Project Overview and History

In 1991, OCIDA and the Syracuse Chamber of Commerce commissioned an Industrial Park Feasibility Study to identify potential candidate sites for locating industrial businesses in Onondaga County. The feasibility study identified two primary candidate locations for large-scale industrial uses, one in the Town of Lysander north of NYS Route 31 and one in the Town of Clay along NYS Route 31 and Caughdenoy Road. The Lysander site was considered less suitable of the two sites due in part to the presence of substantial wetlands and hydric soil conditions. The Clay site was therefore chosen by OCIDA as the more feasible location for development.

OCIDA acquired seven properties that comprised the then-existing approximately 340± acre Park site along Caughdenoy Road. OCIDA then completed an environmental review under the State Environmental Quality Review Act (“SEQRA”) of the Park and any adjoining routes, rights-of-way and areas needed to support the project at that time, including existing and proposed infrastructure and improvements. This review culminated in preparation of a Final Generic Environmental Impact Statement (2013 FGEIS) and OCIDA’s issuance of a Findings Statement that concluded that the creation and P a g e 1.1 Chapter 1 Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021 potential future development of the then existing approximately 340± acre Park avoided or minimized adverse environmental impacts to the maximum extent practicable, and incorporated mitigation measures that were considered practicable.

OCIDA thereafter invested considerable resources in marketing the Park for development. Certain prospective tenants expressed interest in the approximate 340± acre Park over the years but the relatively small size of the current Park was seen as a limiting factor by some. As a result, the Park remains undeveloped. Nevertheless, the Park has many favorable characteristics, including, but not limited to, its proximity to critical utilities and infrastructure, which makes it a very suitable location for large-scale tenants.

This Draft Supplemental Generic Environmental Impact Statement (Draft SGEIS) has been prepared consistent with SEQRA (Article 8 of the Environmental Conservation Law Part 617 of Title 6 of the New York Code of Rules and Regulations). In New York State, most projects of this nature and activities proposed by a state agency or unit of local government, and all discretionary approvals and permits from a state agency or unit of local government, require an environmental impact assessment of a proposed action before such action may be approved, undertaken or funded. SEQRA requires the sponsoring or approving governmental body, in this case OCIDA, acting as SEQRA Lead Agency, to identify, evaluate, and mitigate, to the maximum extent practicable, significant environmental impacts associated with the proposed action. For SEQRA purposes, the term “Project site” used in this document is defined as any

location where project facilities and infrastructure will or might be constructed. The Project site includes an expanded Park consisting of approximately 1250± acres and any adjoining routes, rights-of-way and areas needed to support the Project or Project-related mitigation, including existing or proposed infrastructure and improvements. “Off-site” is defined as any portion of the study areas being assessed for potential impacts that are not on or encompassed by the Project site. Because OCIDA previously prepared the 2013 FGEIS for the Park, this Draft SGEIS evaluates the expanded development footprint of the Park and other changes in circumstances that have the potential to result in any new, previously undisclosed, or unevaluated significant adverse impacts.

1.1.3 Project Purpose and Need

The Project purpose is to expand the Park to enable OCIDA to market the Park to a larger, more diverse mix of potential industrial and commercial developers by making the Project site more attractive to a broader scope of industries, particularly the semiconductor industry, and bringing high tech and high paying jobs to Onondaga County.

This Draft SGEIS identifies, evaluates and addresses various impact thresholds, permit criteria and mitigation measures anticipated for the expanded Park, including those attributes associated with large- scale semiconductor industrial development. By addressing these issues in a Generic EIS format, the SEQRA process will define a set of threshold conditions or criteria under which potential future actions and development will be undertaken or approved, including any subsequent SEQRA compliance requirements.

P a g e 1.2 Chapter 1 Onondaga County Industrial Development Agency Draft Supplemental Generic EIS White Pine Commerce Park May 2021

1.1.4 Project Location and Setting

The Park is located at the northeastern corner of the intersection of NYS Route 31 and Caughdenoy Road in the Town of Clay, Onondaga County, NY (see Figure 1.1-1). The Park is approximately 7 miles north of the City of Syracuse.

The Park is accessible from major nearby interstates. This includes Interstate 81 (I-81) via Exit 30 at NYS Route 31 in Cicero, approximately 2.2 miles east of the Project site. The I-81/I-481/NYS Route 481 interchange is four miles southeast of the project. The NYS Route 481/NYS Route 31 interchange is approximately 3.5 miles west of the Park. The New York State Thruway (I-90) is about 6.5 miles south of the Park. Syracuse Hancock International Airport is about 5 miles south of the Park located along the I-81 corridor.