11.18.25 OCIDA Special Mtg Minutes SIGNED

Document date 2025-11-14 Collected 2026-08-07 Extracted text 2,133 words Format PDF
Official copy ↗ Archived copy Plain text (OCR) Search mentions
From Special
Same source Special · 2025-11-14
Same source Special — OCIDA Recording · 2025-11-14
Same source 11-18-25 OCIDA Special Meeting Agenda · 2025-11-14
Same source Special — OCIDA Mtg Notice 11-18-25 · 2025-11-14

Machine-extracted (OCR) from the official document — formatting is approximate; the official copy governs.

INDUSTRIAL DEVELOPMENT AGENCY
INDUSTRIAL DEVELOPMENT AGENCY
Special Meeting Minutes
November 18, 2025
A Special meeting of the Onondaga County Industrial Development Agency was held on Tuesday,
November 18, 2025, at 401 Montgomery Street, Room #407, Syracuse, New York.
Patrick Hogan called the meeting to order at 9:38 AM with the following in attendance:
PRESENT:
Patrick Hogan
Elizabeth Dreyfuss
Leslie English
Fanny Villarreal
Cydney Johnson
ABSENT:
Susan Stanezyk
Garard Grannell
ALSO PRESENT:
Robert Petrovich, Executive Director
Nate Stevens, Treasurer
Alexis Rodriguez, Secretary
Robert Schoeneck, Assistant Treasurer
Evan Carter, Assistant Secretary
Jeffrey Davis, Esq., Agency Counsel
Amanda Fitzgerald, Esq., Agency Counsel
Prior to addressing the agenda at hand, Patrick Hogan wanted to thank the County Legislature and
County Legislative Chairman, Tim Burtis, for allowing the Agency to use the Chambers. He also
welcomed County Legislator-Elect, Chad Ryan, and County Legislator Charles Garland.
Action Items:
1. Micron New York Semiconductor Manufacturing LLC
Robert Petrovich read the following remarks to be put into the record:
The resolution before the Board today marks the conclusion of the Agency's more than two-
year review of the proposed Micron project under the State Environmental Quality Review
Act, known as SEQRA. On June 14, 2023, along with its application for financial assistance,
OGIDA
INDUSTRIAL DEVELOPMENT AGENCY
Micron submitted to the Agency a full environmental assessment form, otherwise known as
an EAF, in accordance with the mandates of SEQRA that commenced the environmental
review of the proposed Micron project. The proposed Micron project includes, among other
things, the acquisition of an interest in all or a portion of approximately 819 acres of land
located at the westerly side of Burmet Road and the construction of two, approximately 1.2
million square foot memory fabrication facilities.
Micron also proposes to construct a rail spur and construction material conveyance facility to
reduce truck trips and support construction of the Micron campus, a childcare center, a
healthcare center, and a recreation center to serve its employees, and to lease existing
warehouse space within 20 miles of the Micron campus.
In order to ensure that the potential environmental impacts associated with the full build-out
of the Micron campus were fully evaluated, Micron's EAF also covered both the project as
described in Micron's application to the Agency, as well as the construction of all four fabs,
the rail spur site, and childcare site. The Agency completed parts IT and III of the EAF,
declared itself lead agency, and on September the 14th, issued a positive declaration
indicating the need for an environmental impact statement (EIS). From then on, the Agency
spent the next two years evaluating the potential environmental impacts of the proposed
Micron project, as well as various connected actions associated with the utility and
infrastructure improvements necessary to meet the proposed Micron project's electricity,
natural gas, water supply, wastewater, and telecommunications needs.
As part of this process, the Agency worked closely with the CHIPS Program Office, as well
as numerous SEQRA-involved and interested agencies, as well as various federal cooperating
and participating agencies to prepare a Draft EIS and then the Final EIS that the Agency and
the CHIPS program office separately adopted on November 7, 2025.
This process included multiple opportunities for the public to participate, both with respect to
identifying the topics to be studied in the EIS, and also on the contents of the Draft EIS. It
also included significant coordination and consultation with key federal and state agencies,
including the United States Army Corps of Engineers, the United States Fish and Wildlife
Service, the United States Environmental Protection Agency, the New York State
Department of Environmental Conservation, New York State Department of Transportation,
and the New York State Office of Parks and Recreation and Historic Preservation. These
agencies actively participated in the environmental review of the proposed project and
offered their technical advice within the agency's areas of expertise.
Ultimately, the Final EIS identified both short-term construction-related activities and long-
term impacts associated with the preferred action alternative and the no action alternative.
Some impacts were determined not to be significant based on avoidance and minimization
OEIDA
INDUSTRIAL DEVELOPMENT AGENCY
measures. These resource areas included, by way of example, geology, land use, air
emissions.
Other impacts were found to constitute a significant adverse impact. These included, for
example, greenhouse gas emissions, traffic, noise, and wetlands. For these resource areas,
mitigation measures were considered and identified to the maximum extent practicable.
Notwithstanding, as described in the Final EIS, the proposed Micron project will result in
certain unavoidable adverse environmental impacts. These include, but are not limited to, (1)
the permanent loss of approximately 193.38 acres of federal jurisdictional wetlands.
Approximately 174.77 acres of which are state jurisdictional wetlands, and approximately
10.5 acres of non-jurisdictional wetlands, (2) the loss of most of the existing stream channels
currently located in or on the Micron Campus site and the Rail Spur site, (3) the loss of
certain ecological communities, (4) an increase in greenhouse gas emissions in the five-
county area and New York State, (5) significant effects to traffic at certain intersections, and
six, unmitigated traffic-related noise.
Following the Agency's issuance of the Final EIS, agencies and the public were afforded a
reasonable time period to consider the Final EIS. The Agency is now responsible for issuing
its findings statement in accordance with SEQR.
As part of this analysis, the Agency held additional working group sessions to consider these
environmental impacts as presented in the Final EIS, and the various social, economic, and
other essential considerations for which to conduct the required balancing under SEQR. The
Agency found that the preferred action alternative will complete the anticipated development
of the White Pine Commerce Park, bringing its vision to reality and creating numerous
benefits for state and local governments in the form of capstone developments that are
regional destinations, increase tax revenue, and additional economic growth, as well as
fulfilling a need for domestic semiconductor industry growth in the United States.
The Agency also determined that the proposed Micron project will create new infrastructure
in an industry and manufacturing facility of local, state, and national importance, investment
in workforce development, hundreds of construction jobs, and thousands of permanent full-
time positions, and increase sales tax revenue, and thereby advance the job opportunities,
health, general prosperity, and economic welfare of the people of the County of Onondaga
and the state of New York.
Presented with the foregoing, and following numerous workshop sessions over the last two
and a half years, and taking into account public comments and the input of numerous
stakeholders and federal and state agencies with relevant expertise, the Agency carefully and
diligently considered the preferred action alternative and other reasonable alternatives
available, and has considered in detail the social, economic, fiscal, land use, and other
OCIDA
INDUSTRIAL DEVELOPMENT AGENCY
relevant factors as well as the reasonably anticipated environmental impacts and measures to
avoid, minimize, and mitigate impacts of the preferred action alternative, and reasonable
alternatives available. The Agency also has weighed and balanced all relevant environmental
impacts with appropriate social, economic, and other considerations.
The resolution before the Agency, adopting the finding statement, would therefore select the
preferred action alternative for construction and operation of the Micron Semiconductor
Manufacturing Project. The resolution would further certify that the preferred action
alternative is the alternative that, consistent with social, economic, and other essential
considerations, avoids or minimizes potential significant adverse environmental impacts to
the maximum extent practicable, and that such impacts will be avoided or minimized to the
maximum extent practicable by incorporating as conditions, those mitigating measures that
are identified in the Final EIS as practicable.
Patrick Hogan read the Agency action requested, “A resolution of the Board approving the
issuance of a findings statement pursuant to the State Environmental Quality Review Act for
the Micron New York Semiconductor Manufacturing LLC Project.” Motion was made by
Fanny Villarreal, seconded by Elizabeth Dreyfuss. Motion was carried.
Property Disposition Authorization
The Agency desires to lease and/or sell all or a portion of approximately 819.92 acres of real
property located on Burnet Road, Caughdenoy Road and State Route 31 commonly referred
to as the White Pine Commerce Park in the Town of Clay, Onondaga County, New York to
Micron New York Semiconductor Manufacturing LLC for a sale price of $30 million.
R. Petrovich informed the Board that in order for Micron to advance this project, they need to
acquire this property, which has been part of the ongoing process to develop this project and
to allow for construction to begin. The Agency is seeking the Board’s approval to initiate the
process of the 90-day notice and effect the Agency’s Property Disposition Policy in support
of this project.
Patrick Hogan read the Agency Action Requested of “A resolution of the Board authorizing
the lease and/or sale of all or a portion of approximately 819.92 acres of real property located
on Burnet Road, Caughdenoy Road and State Route 31 commonly referred to as the White
Pine Commerce Park in the Town of Clay, Onondaga County, New York to Micron New
York Semiconductor Manufacturing LLC, and execution of documents in connection
therewith, subject to compliance with the Public Authorities Law requirements.” Motion was
made by Elizabeth Dreyfuss, seconded by Leslie English. Motion was carried.
OCIDA
INDUSTRIAL DEVELOPMENT AGENCY
3. Micron New York Semiconductor Manufacturing LLC (Project #3101-23-07A)
Micron New York Semiconductor Manufacturing LLC is proposing to construct and operate
two large-scale, state-of-the-art dynamic random-access memory (DRAM) semiconductor
manufacturing facilities at the White Pine Commerce Park in the Town of Clay. Each fab will
occupy approximately 1.2 million sq. ft. of land and contain approximately 600,000 sq. ft. of
semiconductor cleanroom manufacturing space. The fabs will be supported by central utility
buildings, warehouse space, and product testing space.
Amanda Fitzgerald advised that the PILOT being considered is a deviation from the Agency's
Uniform Tax Exemption Policy. She offered to any representatives from the affected Town,
County, or School District who were present at the meeting to address the Board regarding
such proposed deviation from the Uniform Tax Exemption Policy. There were none.
Alexis Rodriguez stated that OCIDA held a public hearing on November 6, 2025, regarding
the financial assistance requested for the project. At the hearing, (22) public comments were
made. (6) comments were opposed to the financial assistance requested, (6) comments were
in favor of the financial assistance requested, and (10) general comments were made.
A. Rodriguez noted that the North Syracuse Central School District spoke in favor of the
financial assistance requested and provided clarification as to how the PILOT would impact
the taxpayers and the budget of the School District.
A. Rodriguez stated that the recording of the public hearing was sent to the members of the
Board within 24 hours after the hearing was conducted and it was also posted on the
Agency’s website for public viewing within that timeframe.
Patrick Hogan read the Agency action requested, “A resolution of the Board authorizing the
financial assistance the Agency will provide. Agency benefits requested include exemptions
from certain real property taxes, real estate transfer taxes and sales and use taxes.” Motion
was made by Fanny Villarreal, seconded by Elizabeth Dreyfuss. Motion was carried.
4. Micron New York Semiconductor Manufacturing LLC (Rail Spur) (Project #3101-25-
OGA)
Micron New York Semiconductor Manufacturing LLC is proposing to construct a rail spur
and construction material conveyance facility on approximately 38 acres west of 8625
Caughdenoy Road in the Town of Clay to economically transport fill and other aggregate
construction material to the Micron Campus by rail.
Alexis Rodriguez stated that OCIDA held a public hearing on November 6, 2025, regarding
the financial assistance requested for the project. At the hearing (8) public comments were
OGIDA
INDUSTRIAL DEVELOPMENT AGENCY
made. (2) comments were opposed to the financial assistance requested, (3) comments were
in favor of the financial assistance requested, and (3) general comments were made.
A. Rodriguez stated that the recording of the public hearing was sent to the members of the
Board within 24 hours after the hearing was conducted and it was also posted on the
Agency’s website for public viewing within that timeframe.
Patrick Hogan read the Agency action requested, “A resolution of the Board authorizing the
financial assistance the Agency will provide. Agency benefits requested include exemptions
from certain real property taxes, real estate transfer taxes and sales and use taxes.” Motion
was made by Elizabeth Dreyfuss, seconded by Leslie English. Motion was carried.
5. Executive Session
Jeffrey Davis asked to go into executive session for the purpose of discussing pending
litigation.
Motion to enter into executive session was made by Fanny Villarreal, seconded by Elizabeth
Dreyfuss.
Motion to come out of executive session was by Fanny Villarreal, seconded by Cydney
Johnson.
Motion to adjourn was made by Elizabeth Dreyfuss and seconded by Cydney Johnson at 9:59 AM.
Qeaps Kuriquac
Alexis Rodriguez, Secretary