INDUSTRIAL DEVELOPMENT AGENCY
INDUSTRIAL DEVELOPMENT AGENCY
Special Meeting Minutes
November 7, 2025
A Special meeting of the Onondaga County Industrial Development Agency was held on Friday,
November 7, 2025, at 401 Montgomery Street, Room 407 Courthouse, Syracuse, New York.
Patrick Hogan called the meeting to order at 8:33 AM with the following in attendance:
PRESENT:
Patrick Hogan
Susan Stanezyk
Leslie English
Fanny Villarreal
Cydney Johnson
Garard Grannell
ABSENT:
Elizabeth Dreyfuss
ALSO PRESENT:
Robert M. Petrovich, Executive Director
Nate Stevens, Treasurer
Alexis Rodriguez, Secretary
Robert Schoeneck, Assistant Treasurer
Evan Carter, Assistant Secretary
Jeffrey Davis, Esq., Agency Counsel
Yvonne Hennessey, Esq., Agency Counsel
Amanda Fitzgerald, Esq., Agency Counsel
Prior to addressing the agenda at hand, Patrick Hogan thanked the County Legislative Chairman, Tim
Burtis, for allowing the Agency to use the chambers, as well as the rest of the County Legislature.
Action Items:
1. Micron New York Semiconductor Manufacturing LLC Project (3101-23-07A)
Jeffrey Davis gave context to the resolution, explaining that he and Yvonne Hennessey will
give background and pertinent information to the project, then get into the provisions of the
resolve section. He explained that the resolution before the Board is one to consider and
adopt, accepting as complete, the environmental impact statement under SEQR for the
Applicant’s project.
OCIDA
INDUSTRIAL DEVELOPMENT AGENCY
Y. Hennessey said the following:
Micron New York Semiconductor Manufacturing LLC submitted an application to the
Agency for the project, which includes, among other things, the acquisition of an interest in
all or a portion of approximately 806 acres of land located on the White Pine Commerce Park
and the construction of two approximately 1.2 million square foot memory fabrication
facilities. Micron also proposes to construct a rail spur and construction material conveyance
facility to reduce truck trips and support construction of the Micron campus, as well as a
childcare center, healthcare center, and recreational center to service employees. Micron will
also lease existing warehouse space within 20 miles of the Micron campus.
In accordance with the State Environmental Quality Review Act (SEQR), and to assist the
Agency in determining whether the project may have a significant impact upon the
environment, Micron submitted to the Agency an Environmental Assessment Form (EAF), in
order to ensure that the potential environmental impacts associated with the full build-out of
the Micron campus were fully evaluated. This EAF covered both the project as described in
Micron's application to the Agency, as well as the construction of all four fabs, the Rail Spur
site, and the childcare site.
After the Agency reviewed Micron's application and EAF, the Agency declared its intent to
serve as lead agency under SEQR, as well as various connected actions associated with the
utility and infrastructure improvements necessary to meet the proposed project's electricity,
natural gas, water supply, wastewater, and telecommunication needs. No objection to that
notice was received, and on September 14th, 2023, the Agency issued a positive declaration
indicating the need for an Environmental Impact Statement (EIS), issued a draft scoping
document, and scheduled a public scoping meeting.
During the comment period on the draft scoping document, 39 individuals, organizations, and
agencies provided comments. Written letters from the United States Fish and Wildlife
Service and the New York State Department of Environmental Conservation were received.
The Agency considered each comment received during this comment period to determine the
final scope of the Draft EIS, and to inform the related technical analysis and environmental
resources to be evaluated in that EIS.
On December 14th, 2023, the Agency adopted the final scope, and a copy of that final scope
is included in Appendix A2 of the Final EIS before you.
Thereafter, the Agency, with the assistance of Micron, its consultants, and the CHIPS
program office, jointly prepared a Draft EIS to evaluate the potential environmental effects of
the proposed Micron project as required under both SEQR and the National Environmental
Policy Act, NEPA. The Draft EIS evaluated various alternatives for the proposed Micron
project. It also described the affected environment as it currently exists, and then analyzed
INDUSTRIAL DEVELOPMENT AGENCY
the environmental consequences of the no-action alternative, and then of the preferred action
alternative.
The resource areas evaluated included land use, zoning and public policy, geology, soils and
topography, water resources, biological resources, historic and cultural resources, air quality,
greenhouse gas emissions, climate change and climate resiliency, solid waste, hazardous
waste and hazardous materials, human health and safety, utilities and supporting
infrastructure, transportation and traffic, noise and vibration, visual effects and community
character, community facilities, open space and recreation, socioeconomic conditions, and
environmental justice.
The Draft EIS also analyzed potential impact avoidance, minimization, and mitigation
measures, as well as the potential cumulative environmental effects of the project with other
past, present, and reasonably foreseeable future actions unrelated to the proposed project.
During development of the Draft EIS, the Agency regularly consulted with other involved
and interested agencies, including but not limited to the New York State Department of
Environmental Conservation and the New York State Department of Transportation. This
was done to ensure that all environmental impacts were identified and fully evaluated in the
Draft EIS. At the same time, the CHIPS program office regularly consulted with
participating and cooperating agencies under NEPA, including but not limited to the United
States Environmental Protection Agency and the United States Army Corps of Engineers.
The Agency also created a working group to understand and evaluate the proposed Micron
project and all potentially significant environmental impacts including available avoidance,
minimization, and mitigation measures, as well as to consider and assess preliminary drafts
of the Draft EIS. During May and June of this year, Agency staff held numerous working
group sessions, during which the Agency's council and consultants discussed each
environmental resource area evaluated in the Draft EIS and addressed all questions.
Thereafter, the Agency adopted a resolution on June 25th, 2025, determining the Draft EIS to
be complete and adequate for the purposes of commencement of public review. The Agency
also adopted a public hearing resolution and published a notice of availability, announcing a
45-day comment period for the public to comment on the Draft EIS, and providing notice that
public hearings would take place to accept verbal comments on Draft EIS on July 24" , 2025,
from 10 a.m. to 1 p.m., 2 p.m. to 5 p.m., and 6 p.m. to 9 .p.m. at the Liverpool High School
Auditorium in Liverpool, New York. Comments on the draft EIS were accepted in writing,
either by first-class mail or electronic mail, or as part of the July 24th public hearing.
At the public hearings, everyone who wished to speak was given the opportunity to do so,
and some individuals spoke multiple times. Overall, there were a total of 97 speakers at the 3
public hearing sessions. For both written and oral comments, there were a total of
approximately 1,270 comment submissions received from the general public on the Draft
INDUSTRIAL DEVELOPMENT AGENCY
EIS. Some of them were duplicates, and we had a total of 1,050 commenters. Of these, 850
were form letters. These comments included three comments from local elected officials and
12 comments from federal, state, and local agencies. Many of the comments were in support
of the project and connected actions, while others were opposed.
Although not all of the commenters provided their location, of those that provided a location,
over 650 of the 1,050 commenters were from outside the five-county Central New York
region. The non-local comments came from other locations in the state of New York, other
states, as well as other countries, such as Ireland, England, Slovenia, and Italy.
Following the close of the comment period, the Agency again worked with its consultants,
the CHIPS program office, and Micron, as well as other involved agencies, to address all
comments received on the Draft EIS, and to prepare a Final EIS. As part of this, the CHIPS
program office, again, consulted with participating and cooperating agencies, such as the
Environmental Protection Agency and the Army Corps of Engineers.
The Final EIS incorporates certain changes from the Draft EIS including a potential revision
to the proposed Micron project's construction schedule and commencement of construction
for each fab, as well as the childcare site, compared to what was presented in the Draft EIS.
The recent decision by the New York Independent Systems Operator that a new electrical
substation would be required for operations of Fab 2 as well as other changes in response to
the Agency and public comments. A redline version of the Final EIS, identifying the changes
that were made, will be available as part of the Final EIS on the Agency's website.
In response to public comments, the Final EIS also includes a new appendix expanding on
the discussion in the Draft EIS on the proposed use, management, and disposal of PFAS, by
the proposed Micron project. This new appendix is Appendix L1.
The Final EIS also includes a summary of all the comments received on the Draft EIS, as
well as the Agency's full Responsiveness Summary that responds to each of the public
comments on the proposed project and the Draft EIS. A copy of this Responsiveness
Summary is in Appendix A5.
Agency staff also has held additional working group stations, during which the Agency's
counsel discussed the process and the changes from the Draft to Final EIS and addressed all
questions.
Following the Agency's issuance of the Final EIS, agencies and the public will be afforded a
reasonable period of time, not less than 10 calendar days in which to consider the Final EIS.
7 and I i’
ONONDAGA COUNTY
INDUSTRIAL DEVELOPMENT AGENCY
Thereafter, the Agency will issue a finding statement in accordance with SEQRA that
considers the relevant environmental impacts presented in the Final EIS, weighs and balances
them with social, economic, and other essential considerations, provides a rationale for the
Agency's decision, and certifies that the requirements of SEQRA have been met.
J. Davis noted that Y. Hennessey summarized the “whereas” clause stated in the resolution.
J. Davis read the following:
Therefore, be it resolved by the members of the Onondaga County Industrial Development
Agency: Section 1, the Agency hereby confirms its status as SEQRA lead agency concerning
the Coordinated Environmental Review for the proposed Micron project. The Agency
determines and finds that the Final EIS dated November 2025 is complete.
The Agency determines that none of the changes from the Draft EIS to Final EIS materially
change the reasonably foreseeable effects that were described in the Draft EIS for the
proposed Micron project, or alter the significance of those effects.
The Agency hereby adopts a Notice of Completion of the Final EIS concerning the proposed
Micron project, which is attached as Exhibit A to the resolution.
The Agency shall arrange for filing and distribution of the Notice of Completion and Final
EIS pursuant to the requirements of SEQR. Copies of the Final EIS and Notice of
Completion, as well as a copy of this resolution, will be placed on file in the office of the
Agency, where the same shall be available for public inspection during business hours, and
an electronic copy will also be made available for public viewing at the Onondaga County
Public Library. The Agency will post the Final EIS on its website.
The Agency shall undertake such other action as may be necessary and desirable to comply
with SEQR. The Chairman and Executive Director of the Agency are authorized or directed
to distribute copies of the resolution, and to do so and further, perform any other acts that
may be necessary, to implement the provisions of the resolution.
Finally, the resolution shall take effect immediately.
Patrick Hogan read the Agency Action Requested (a) of “A resolution of the board accepting
as complete pursuant to the State Environmental Quality Review Act (SEQRA) the Final
Environmental Impact Statement (FEIS) prepared for the Micron New York Semiconductor
Manufacturing LLC Project, and authorizing the filing and distribution of the Notice of
Completion and FEIS pursuant to the requirements of SEQRA.” Motion was made by Susan
Stancezyk, seconded by Garard Grannell. Motion was carried.
OCIDA
INDUSTRIAL DEVELOPMENT AGENCY
Patrick Hogan read the Agency Action Requested (b) of “A resolution of the board authorizing
and directing Agency staff and counsel to take various actions pursuant to the Eminent Domain
Procedure Law for the potential acquisition of lands, easements and rights in support of the
development of the Micron New York Semiconductor Manufacturing LLC Project and the
White Pine Commerce Park.” Motion was made by Susan Stanczyk, seconded by Leslie
English. Motion was carried.
Before adjourning, Patrick Hogan thanked everyone for their hard work on this project, especially the
staff of the Economic Development Office, the County Legislature, and the County Executive, who
brought this project to the County.
Motion to adjourn was made by Susan Stanczyk and seconded by Cydney Johnson at 8:48 AM.