Notice of Complete Application - Micron NY Dam Safety NOCA - NYSDEC
Notice of Complete Application - Micron NY Dam Safety NOCA - NYSDEC
Legal
Attached.
Document
Micron NY Dam Safety NOCA - NYSDEC 06-17-2026.pdf
284.56 KB
...Please be advised that your application for a DEC permit(s) is complete and a technical review
has commenced. Notice and the opportunity for public comment is required for this application. Enclosed
is a Notice of Complete Application for your...
...Please be advised that your application for a DEC permit(s) is complete and a technical review
has commenced. Notice and the opportunity for public comment is required for this application. Enclosed
is a Notice of Complete Application for your...
(B) to authorize the mapping, site plan and legal work necessary to submit
application to the Town and complete the Town process for the Zone Change.
Section 5. This Resolution shall take effect immediately upon adoption.
The question of the...
(B) to authorize the mapping, site plan and legal work necessary to submit
application to the Town and complete the Town process for the Zone Change.
Section 5. This Resolution shall take effect immediately upon adoption.
The question of the...
24 results in minutes for “"Complete Application"”
...The chairman said the Check Off Sheet provided to the applicant for submission must be complete before
the applicant comes before the planning board. He reminded applicants to adhere to this process.
...Tips for completing Part 2:
* Review all of the information provided in Part 1. .
e Review any application, maps, supporting materials and the Full EAF Workbook. oO _
e Answer each of the 18 questions in Part 2.
¢ Ifyou answer “Yes...
Motion Carried 7-0
Gloria Wetmore
Agency Use Only [If applicable]
Full Environmental Assessment Form Project : [Fox Dealership Sto tan
Part 2 - Identification of Potential Project Impacts date: [January 25, 2017
Part 2 is to be completed by the lead...
...The Onondaga County Department of Transportation has determined that
the applicant must complete a drainage study or Stormwater Pollution
Prevention Plan (SWPPP) to meet Department requirements verifying that
the proposed development would not create additional stormwater runoff into
the County...
...Board Secretary
Agency Use Only [If applicable]
Full Environmental Assessment Form Project : ferPank Rood Solar- North and South |
Part 2 - Identification of Potential Project Impacts Dac: fanaytamaz |
Part 2 is to be completed by the lead agency. Part 2 is...
...Add parking calculation to Zoning Regulation Chart on Drawing 1.
-Completed
2. Add note on Drawing 5, Elevations, that singage as shown is not part of the site plan
approval. A separate application for sign approval must be submitted.
-Completed...
...In the event of default, and following notice and expiration of any
applicable cure period, the Town may draw upon such financial assurance to complete
decommissioning.and restoration of the site in accordance with the approved plan.
...attorney, Robert Germain,
and the applicant attorney have reviewed the decommissioning plan with C&S Engineers and
have an understanding that no Certificate of Occupancy (CO) will be issued until the
decommissioning plan is complete, securities in place and approved...
...The applicant stated the following:
1. Seals on all drawings are now uniform and complete. One set is totally complete.
2. Second fire hydrant has been added to the plans. Email from Paul Linnitz confirms this.
...Liebi asked if the signage on the building was complete.
Mr. Pavek stated if the varainces are approved, the signage and building will be complete.
Mrs. Liebi asked what the signage changes were.
The applicant stated they would add two...
...The applicant may submit materials immediately following PDD concept plan acceptance
by the Town Board. All materials shall be prepared and completed to the satisfaction of the
Planning Board.
({c)
Review schedule. Unless otherwise specified by the Town Board, the...
...and Romans and Kevin Berry the applicant were present. Hal Romans
presented the plan. Mr. Romans said there are no changes from the preliminary plat. Chairman
Lepkowski asked when Lawton Road would be complete. Mr. Berry said they have been...
...R-16-186 Authorization/Application (A) State and Municipal Facilities Program
(SAM)(three pavilions):
Councilor Bick moved the adoption of a resolution approving the application for the
State and Municipal Facilities Program (SAM) for the construction of (3) three
pavilions...
...The applicant has
submitted Part 1 of the Full Environmental Assessment Form and amended it to address
questions brought up during the Planning Board work sessions. We believe that this form is now
complete and accurate for the Town Board...
The site trip generation was completed using a trip generation study that was completed for the
two Chick-fil-A’s in Onondaga County. Trip generation data for that study was collected in
November 2021 and July 2022. A portion...
...applications for the Battery Storage Systems
(items numbered 13,14 and 15 on the agenda) will be adjourned because the wording
for the Local Law titled Town of Clay Battery Energy Storage System Law has
not yet been completed and...
REGULAR MEETING OF THE TOWN BOARD – December 19th, 2016
Town of Clay
Page 3 of 8
3
Tim Coyer of Ianuzi and Romans was present on behalf of the applicant. Mr. Coyer
began by explaining that the applicant wishes to...
...this Board to complete the sale; we know they will need to be
back in front of us for a complete Site Plan review and Special Permit should this site become a Medical Office.
The Applicant stated at a minimum...
...of property not owned by applicant was addressed. They spoke with Ken Ermiger,
owner of the 60-foot strip, and he does not want people walking on his property. There is a
concern for emergency access completely around the building.
...The traffic study is complete and is being reviewed by the County Department of Transportation.
Mr. Romans provided a density sketch that is based on 266 lots at R-15 zoning. The applicant is
proposing 225 homes and is estimating...
...from plan just leave location — separate application required Removed from plan
Add Parking requirements and what is provided to plan Added to plan
Need complete set of plans — cover page, grading, Landscaping Completed, submitted to C&S on Oct. 5...
...Coyer said the applicant has
completed the long form EIS (Environmental Impact Study) and has a mitigation
plan and they are making an effort to preserve some trees.
There being no more questions or comments, Deputy Supervisor Bick closed the