Key Actions & Decisions
-
◆
Public hearings opened for Nexamp BESS projects on Wetzel Rd and Longbranch Rd (Case #1243, #1244).
-
◆
Public hearings opened for Summit Federal Credit Union zone change and special permits (Case #1240, #1241, #1242).
-
◆
Multiple public hearings adjourned to March 2, 2026, to allow for Planning Board review.
-
◆
Residents voiced strong opposition to battery storage sites citing fire risks and volunteer firefighter strain.
-
◆
Board directed Nexamp to provide a decommissioning plan for the battery sites.
The Town Board opened public hearings for two proposed battery energy storage systems (BESS) on Wetzel and Longbranch roads, while a proposal for a new Summit Federal Credit Union on Taft Road was met with fewer questions. Residents and fire officials raised significant concerns regarding emergency response times for the battery projects.