Micron Support Facility to Reduce Truck Traffic; Planning Board Reviews Site Plan
2025-09-24 · 3132 words
Key Actions & Decisions
-
◆
RailWorks Presentation: Board received a preliminary presentation on a 38-acre rail spur facility at 8625 Caughdenoy Road to support Micron construction via rail rather than truck.
-
◆
Windsor Property Group: Unanimously approved the preliminary and final plat for a business park at 7985 Morgan Road (Case #2025-021, #2025-022).
-
◆
Byrne Dairy: Continued review of site plan adjustments for 7190 Buckley Road to October 8, pending lighting plan sign-off from Onondaga County.
-
◆
Canandaigua National Bank: Continued site plan review for 7515-7519 Oswego Road to October 8 to finalize engineering details and landscaping.
-
◆
Northern Credit Union: Adjourned site plan and special permit review for 5004-5008 West Taft Road to October 8.
-
◆
Chad Mutter: Adjourned EV charging station site plan for 7293 Buckley Road to November 19; no applicant present.
-
◆
Morgan Road Business Park: Adjourned site plan review to November 19.
-
◆
Rich Family Subdivision: Adjourned zone change referral for 8100-8101 Oasis Lane to October 8.
The Town of Clay Planning Board reviewed plans for a $44 million rail spur facility intended to supply aggregate materials for the Micron chip fabrication plant. The board also advanced subdivision plats for a Morgan Road business park and addressed site plans for a Byrne Dairy expansion and a new Canandaigua National Bank branch.